Samiksha Jaiswal (Editor)

Gotthard Base Tunnel

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Line
  
AlpTransit

Opened
  
1 June 2016

Cross
  
Swiss Alps

Gotthard Base Tunnel Gotthard Base Tunnel Wikipedia

Official name
  
German: Gotthard-BasistunnelItalian: Galleria di base del San GottardoRomansh: Tunnel da basa dal Son Gottard

Location
  
Switzerland (Uri, Graubünden, and Ticino)

Status
  
Active since 11 December 2016

System
  
Swiss Federal Railways (SBB CFF FFS)

Crosses
  
Swiss Alps (western Glarus Alps and central Lepontine Alps at the eastern Gotthard Massif)

Electrified
  
15 kV AC railway electrification

Similar
  
Gotthard Tunnel, Gotthard Pass, Lötschberg Base Tunnel, Seikan Tunnel, Saint‑Gotthard Massif

The gotthard base tunnel in switzerland made in germany


The Gotthard Base Tunnel (GBT; German: Gotthard-Basistunnel, Italian: Galleria di base del San Gottardo, Romansh: Tunnel da basa dal Son Gottard) is a railway base tunnel through the Alps in Switzerland. It opened on 1 June 2016, and full service began on 11 December 2016. With a route length of 57.09 km (35.5 mi), it is the world's longest and deepest traffic tunnel and the first flat, low-level route through the Alps.

Contents

The project consists of two single-track tunnels connecting Erstfeld (Uri) with Bodio (Ticino) and passing below Sedrun (Graubünden). It is part of the AlpTransit project, also known as the New Railway Link through the Alps (NRLA), which also includes the Ceneri Base Tunnel further south (scheduled to open late 2020) and the Lötschberg Base Tunnel on the other main north-south axis. The base tunnel bypasses most of the Gotthard Railway, a winding mountain route opened in 1882 across the Saint-Gotthard Massif, which is now operating at capacity. It establishes a direct route usable by high-speed rail and heavy freight trains. It is the third tunnel connecting the cantons of Uri and Ticino after the Gotthard Tunnel and the Gotthard Road Tunnel.

Gotthard Base Tunnel World39s longest railway tunnel in Switzerland will travel at 155mph

The main purpose of the Gotthard Base Tunnel is to increase local transport capacity through the Alpine barrier, especially for freight, notably on the Rotterdam–Basel–Genoa corridor, and more specifically to shift freight volumes from trucks to freight trains. This not only significantly reduces the danger of fatal road crashes involving trucks, but also reduces the environmental damage caused by the ever-increasing amount of freight hauled by heavy trucks. The tunnel provides a faster connection between the canton of Ticino and the rest of Switzerland, as well as between northern and southern Europe, cutting the ZürichLuganoMilan journey time for passenger trains by one hour (and from Lucerne to Bellinzona by 45 minutes).

Gotthard Base Tunnel World39s longest railway tunnel about to open in Switzerland

After 64 percent of Swiss voters accepted the AlpTransit project in a 1992 referendum, tunnel construction began in 1996. Drilling operations in the eastern tunnel were completed on 15 October 2010 in a breakthrough ceremony broadcast live on Swiss TV, and in the western tunnel on 23 March 2011. The tunnels' constructor, AlpTransit Gotthard AG, originally planned to hand over the tunnel to Swiss Federal Railways (SBB CFF FFS) in operating condition in December 2016 but, on 4 February 2014, the handover date was changed to 5 June 2016 with the start of an 850-day opening countdown calendar on the AlpTransit homepage. The total projected cost of the project was 9.8 billion Swiss francs (€8.85 billion, US$10.3 billion); the final cost exceeded $12 billion. Nine people died during construction.

Gotthard Base Tunnel World39s longest tunnel completed Business Insider

Background

Gotthard Base Tunnel wwwtelegraphcoukcontentdamTravel2016maygo

Since the 13th century, the 2,106 metre-high Gotthard Pass has been an important trade route from northern to southern Europe. Control of its access routes led to the birth of the Swiss Confederacy. The Gotthard Pass is located halfway between Lake Lucerne and Lake Maggiore. It is the shortest link between the navigable Rhine and the Po. In 1882, with the inauguration of the Gotthard Railway Tunnel, the travel time between Altdorf and Biasca was reduced dramatically, from about 30 hours (using stagecoaches) to only a few hours. This time was reduced further with the opening of the Gotthard Road Tunnel in 1980.

Gotthard Base Tunnel Gotthard Base Tunnel Wikipedia

Today both the rail, and the road, routes are among the most important passages through the Alps on the north-south axis.

After the opening of the auto tunnel, in 1980, traffic increased more than tenfold, and the existing tunnel was at its capacity limits by 2013. A second tunnel will be built next to the first, as per a national referendum. Construction is to start in 2020 and finish in 2027.

As early as 1947, the engineer Eduard Gruner imagined a two-story base tunnel from Amsteg to Biasca, both rail and road, with a stop at Sedrun, to provide a faster and flatter passage through the Swiss Alps. Similarly to Gruner's idea, the GBT cuts through the Gotthard Massif some 600 m (2,000 ft) below the older tunnel. On the current track, the Gotthard Railway, only trains up to 1,300 t (1,400 short tons; 1,300 long tons) when using two locomotives or up to 1,500 t (1,700 short tons; 1,500 long tons) with an additional bank engine at the end of the train are able to pass through the narrow mountain valleys and through spiral tunnels climbing up to the portals of the old tunnel at a height of 1,151 m (3,776 ft) above sea level. When the GBT is in full service, standard freight trains of up to 3,600 t (4,000 short tons; 3,500 long tons) will be able to pass this natural barrier.

Because of ever-increasing international truck traffic, Swiss voters chose a shift in transportation policy in February 1994 (Traffic Transfer Act, enacted in October 1999). A second law, the Alpine Protection Act of 1994, required a shift of as much tonnage as possible from truck transport to train transport.

The goal of both the laws is to transport trucks, trailers and freight containers through Switzerland, from Basel to Chiasso, and beyond by rail to relieve the overused roads, and that of the Gotthard in particular, by using intermodal freight transport and rolling highways (where the entire truck is transported). The GBT substantially contributes to the requirements of both laws and enables a direct flat route from the ports of the North Sea (notably Rotterdam) to those of the Mediterranean Sea (notably Genoa), via the Rhine corridor.

Passenger trains can travel up to 250 km/h (155 mph) through the GBT, currently reducing travel times for trans-Alpine train journeys by about 40 minutes, and by one hour once the adjacent Zimmerberg and Ceneri Base Tunnels are completed. This is viewed as a revolution, especially in the isolated region of Ticino, which is separated from the rest of the country by the Alps and the Gotthard. The two stations of Bellinzona and Lugano (respectively named "Gate of Ticino" and "Terrace of Ticino") were entirely renovated for the opening of the GBT, among other improvements.

As of 2016, the Gotthard Base Tunnel is the longest railway tunnel in the world. It is the third Swiss tunnel to bear this title, after the Gotthard Tunnel (15 km, 1882) and the Simplon Tunnel (19.8 km, 1905). It is the third tunnel built under the Gotthard, after the Gotthard Tunnel and the Gotthard Road Tunnel.

Description

The Gotthard Base Tunnel is, with a length of 57.09 kilometres (35.47 mi) and a total of 151.84 km (94.3 mi) of tunnels, shafts and passages, the longest railway tunnel in the world, with a geodetic distance of 55.782 kilometres (34.661 mi) between the two portals. It is also the first flat route through the Alps or any other major mountain range, with a maximum height of 549 metres (1,801 ft) above sea level, corresponding to that of Berne. It is the deepest railway tunnel in the world, with a maximum depth of 2,450 metres (8,040 ft), comparable to that of the deepest mines on Earth. Without ventilation, the temperature inside the mountain reaches 46 °C (115 °F).

Like the two other tunnels passing below the Gotthard, the Gotthard Base Tunnel connects two Alpine valleys across the Saint-Gotthard Massif: the Urner Reusstal in the canton of Uri, in which flows the river Reuss, and the Valle Leventina, the largest valley in the canton of Ticino, in which the river Ticino flows. Unlike most other tunnels, the Gotthard Base Tunnel passes under several distinct mountain massifs, two of them being major subranges of the Alps, the Glarus Alps and the Saint-Gotthard Massif, with the valley of the Anterior Rhine, the Surselva in the canton of Graubünden, between them. The tunnel passes under these two ranges more than 2 kilometres (1.2 mi) below the Chrüzlistock (2,709 m (8,888 ft)) and the Piz Vatgira (2,983 m (9,787 ft), near the Lukmanier Pass). While the cantons of Uri and Ticino are part of the German- and Italian-speaking areas of Switzerland respectively, the Surselva is mainly Romansh-speaking.

The Alps strongly influence the European climate – and that of Switzerland in particular – and there can be substantially different weather conditions at each end of the GBT, described by the Ticinese architect Mario Botta: "The light changes at the Gotthard: that of the Mediterranean Sea is not the same as that of the continent, that of the central lands, that of Europe far away from the sea." On average, the temperature is 2 to 3 °C (4–5 °F) higher on the south side than the north side, but on some days, temperature differences are well over 10 °C (18 °F).

The north portal lies in the north of the municipality of Erstfeld at an elevation of 460 metres (1,510 ft), east of the Reuss. There, the tunnel penetrates the western slopes of the Bälmeten and Chli Windgällen (although only marginally) before passing below the valley of the Chärstelenbach, a creek in the Maderanertal. From there, the tunnel runs parallel to the small valley of Etzli, below the Witenalpstock. The main crest of the Glarus Alps, which is the watershed between the Reuss and the Anterior Rhine, is crossed below the Chrüzlistock, the crest having an elevation of about 2,700 metres (8,900 ft) at this point. From the crest and border, the tunnel runs parallel to the small valley of the river Strem (Val Strem) before passing below Sedrun and the Anterior Rhine. From the bottom of the valley, the tunnel proceeds towards the valley of the Rein da Nalps (Val Nalps) and passes east of Lai da Nalps, before crossing the Gannaretsch range below the western summit of Piz Vatgira (2,981 metres (9,780 ft)). This is the deepest point of the tunnel, with a rock layer of 2,450 metres (8,040 ft) above it. The tunnel then passes below the valley of the Rein da Medel (Val Medel) and west of Lai da Sontga Maria. After a few kilometres the tunnel crosses the watershed between the Anterior Rhine and the Ticino, just north of Pizzo dell'Uomo (2,525 metres (8,284 ft)). This point corresponds to the main chain of the Alps, and is the main drainage divide between the Rhine and the Po. For a few kilometres, the tunnel passes below two western tributaries of the Brenno in the Valle Santa Maria before crossing the last range, west of the Passo Predèlp (about 2,500 metres (8,200 ft)) and east of Faido. It then follows the eastern slopes of the large Valle Leventina, the valley of the Ticino, for about 18 kilometres (11 mi) to the south portal at Bodio, at an elevation of 312 metres (1,024 ft), just 3 kilometres (1.9 mi) before Biasca, where the Brenno converges with the Ticino.

The closest railway stations to the portals are Altdorf and Biasca. The first regularly served railway stations on the base line (as of 2016/17) are those of Arth-Goldau (Schwyz), a railway node with links to Lucerne and Zürich, and Bellinzona (the "Gate of Ticino"), with links to Locarno, Luino and Lugano (via the Monte Ceneri Rail Tunnel). The journey from Arth-Goldau to Bellinzona takes not more than an hour. The station of Altdorf is planned to be served by 2021. There also have been talks of using that of Biasca. The travel between Altdorf and Biasca would last less than 25 minutes.

Construction

AlpTransit Gotthard AG was responsible for construction. It is a wholly owned subsidiary of the Swiss Federal Railways (SBB CFF FFS).

To cut construction time in half, four access tunnels were built so that construction could start at four different sites simultaneously: Erstfeld, Amsteg, Sedrun, and Faido. A fifth at Bodio was added later. The two tunnels are joined approximately every 325 m (1,066 ft) by connecting galleries. Trains can move between the tunnels in the two multifunction stations at Sedrun and Faido. These stations house ventilation equipment and technical infrastructure and serve as emergency stops and evacuation routes.

Access to the Sedrun station site is by a level access tunnel 1 km (0.6 mi) long from the valley floor near Sedrun. At the end of the access tunnel, two vertical shafts lead 800 m (2,625 ft) down to the base tunnel level. A proposal to construct a functioning railway station, called Porta Alpina (from Romansh, "Alpine Gate"), at this site was evaluated, but the project was put on hold in 2007 and definitively cancelled by the federal authorities in 2012 as uneconomical.

The final breakthrough in the east tube occurred on 15 October 2010 at 14:17 +02:00. The final breakthrough in the west tube occurred on 23 March 2011 at 12:20.

On 30 August 2013, the tunnel was entirely traversed for the first time from Bodio to Erstfeld in six hours, by diesel train, buses and by foot.

On 16 December 2013, the operational test phase started on a 13-kilometre (8.1 mi) stretch in the southern section of the west tube between Faido and Bodio. Its purpose was to test the infrastructure and any ancillary systems.

On 31 October 2014, the railway track installation was completed. A gold sleeper on the very last part of the track was installed during the event to mark this milestone of progress.

On 1 October 2015, following the permission by the Federal Office of Transport, the first tests on the entire length of the GBT were performed, with steadily increasing speed. On 8 November, a train reached the top speed of 275 km/h.

Allocation of work

The contracts were awarded in sections:

  • Erstfeld (the 7.7 km (4.8 mi) section from Erstfeld to Amsteg), with two tunnel boring machines (TBM) boring the two tubes. The break-through of the east tube between Erstfeld and Amsteg took place on 15 June 2009. The portal area was surface-mined.
  • Amsteg (the 11.3 km (7.0 mi) section from Amsteg to north of Sedrun), ARGE AGN (Strabag and Züblin Murer) received the contract for work in this sector. On 9 December 2009, the Amsteg section was officially delivered to the owner for fitting-out, with civil engineering, construction, concrete and lining work completed in early 2010.
  • Sedrun (the 8.6 km (5.3 mi) East tube and 8.7 km (5.4 mi) West tube in the section immediately north and south of Sedrun), along with work performed by Transco (Bilfinger SE, Implenia, Frutiger and Impresa Pizzarotti). The final breakthrough in the west tube occurred in March 2011. The northbound tubes from Amsteg to the Sedrun multifunction station (north) were handed over to the railway systems contractor Transtec Gotthard on 15 September 2011, the date specified in the construction schedule.
  • Faido (13.4 km (8.3 mi) East tube and 13.6 km (8.5 mi) West tube in the section from south of Sedrun to Faido), with Consorzio TAT (Alpine Mayreder Bau, CSC Impresa costruzioni, Hochtief and Implenia and Impregilo).
  • Bodio (15.9 km (9.9 mi) East tube and 15.6 km (9.7 mi) West tube in the section from Faido to Bodio), with work performed by Consorzio TAT (Alpine Mayreder Bau, CSC Impresa costruzioni, Hochtief, Implenia and Impregilo). Civil engineering construction, concrete and lining works were completed in early 2010.
  • Deaths during construction

    Nine workers lost their lives during construction; one in the Amsteg section, two in the Sedrun section, and three each in the southernmost Faido and Bodio sections. These were:

  • On 8 June 2000, a worker from Germany, the first victim of the tunnel construction, was hit by a boring bar that fell down 700 m.
  • On 12 March 2002, a worker from South Africa was buried by excavation material .
  • On 3 April 2003, a worker from Germany was hit by a rock.
  • On 11 September 2003, a worker from Austria was killed by being crushed by a toppling cable drum.
  • On 21 January 2005, a worker from Italy and another from Switzerland were hit by a colliding mine train.
  • On 23 November 2006, a worker from Germany, was crushed to death by a mine train.
  • On 24 June 2010, a worker from Germany was catapulted out of an inspection train.
  • On 16 July 2012, a worker from Italy fell from a scaffold.
  • Politics

    The realization of the GBT, as the centrepiece of the NRLA, is also a prototypical example of direct democracy in Switzerland. In order to accomplish this mega-project the political institutions also had to overcome many parliamentary sessions and several major popular votes, including the following:

  • 27 September 1992, NRLA proposal (optional referendum): The final proposal by the Federal Council was accepted by 63.6% yes votes (declined by 1+2/2 cantons, turnout 45.9%)
  • 20 February 1994, Alps Initiative (federal popular initiative): Initiated by a few private people with the goal to protect the Alpine environment from the negative impact of traffic was accepted by 51.9% yes votes (declined by 7 cantons, turnout 41%). The initiative was accepted despite the recommendation by the Federal Council from 12 February 1992 to decline the initiative without any counterproposal, and despite the parliamentary recommendation (both chambers) from 18 June 1993 to decline the initiative.
  • 29 November 1998, Public Transport Funding (mandatory referendum): A total budget of CHF 30 billion for several public transport projects was accepted by 63.5% yes votes (declined by 1+3/2 cantons, turnout 38.3%); "the NRLA is to receive CHF 13.6 billion"
  • 21 May 2000, Bilateral EU Agreements / 40-tonne Trucks / Heavy Traffic Fee (optional referendum): As part of a whole package of several bilateral agreements with the EU the Swiss also accepted by 67.2% yes votes (declined by 2 cantons, turnout 48.3%) the shift of an upper limit for trucks from 28 tonnes to 40 tonnes, but at the same time the EU agreed to a new heavy-traffic fee, which will also be used to finance the NRLA
  • 17 December 2003, Ceneri Base Tunnel (parliamentary session): The controversial funding of the Ceneri Base Tunnel was finally passed by parliamentary approval only; the possibility for an optional referendum was not raised by any political groups, nor by the public. The then-in-charge transport minister, Federal Councilor Moritz Leuenberger, was quoted as saying "This is the only way to make the railway [the Gotthard axis] a flat line between Basel and Chiasso."
  • Inauguration and commissioning

    In 2016, several events, including festivities and special exhibitions, were held around the Gotthard. These culminated at the inaugurations in early June, dubbed Gottardo 2016. Many public institutions joined the celebrations, such as Swiss Post, which produced a special stamp for the Gotthard Base Tunnel, and Swissmint, which issued gold and silver coins dedicated to the opening.

    On 31 May 2016, a day before the inauguration, the nine people who died during construction were commemorated in a ceremony at the north portal in Erstfeld that was led by a Catholic vicar general, a vicar of the Evangelical-Reformed Church of Uri, a Jewish rabbi, and a Muslim imam. A bronze memorial plaque with their names — four coming from Germany, three from Italy, and one from each of South Africa and Austria – was unveiled by AlpTransit Gotthard CEO Renzo Simoni. A Catholic shrine to Saint Barbara, the patron of miners, stands inside the tunnel as a memorial.

    The tunnel was officially inaugurated on 1 June 2016. At the northern entrance in Erstfeld, President of the Confederation Johann Schneider-Ammann spoke of a "giant step for Switzerland but equally for our neighbours and the rest of the continent", while a live relay carried a speech given by Transport Minister Doris Leuthard at the southern entrance in Bodio. The first journey carried hundreds of Swiss citizens who had won tickets in a draw, while the assembled guests in Erstfeld, including the Federal Council in corpore, heads of state and government from neighbouring countries and transport ministers from European countries, attended the opening show Sacre del Gottardo by Volker Hesse featuring dancers, acrobats, singers and musicians celebrating Alpine culture and history. On the following weekend, popular festivities and special exhibitions, attended by more than 100 000 visitors, were held.

    Gottardino special trains

    From 2 August to 27 November 2016, the Swiss Federal Railways ran a special train service through the tunnel called "Gottardino" which was open to the public. It was a once-daily service from Flüelen railway station to Biasca railway station and in reverse. The trains make a stop inside the tunnel to allow passengers to visit an exhibition inside an underground multifunction station in Sedrun which would normally be used in emergency only.

    Regular services

    In the year 2016, the GBT was tested extensively before its integration into the regular schedule on 11 December. On 5 December, the Swiss Federal Railways were granted permission from the Federal Transport Office to use the new base line. While the base tunnel is used for InterCity trains (ICN) and EuroCity trains (EC), the summit line remains in use for regional trains.

    Figures

  • Length:
  • Total: 151.840 km (94.349 mi)
  • Western tube: 57.017 km (35.429 mi)
  • Eastern tube: 57.104 km (35.483 mi)
  • Diameter of each of the single-track tubes: 8.83–9.58 m (29.0–31.4 ft)
  • Distance between cross passage tube: ca. 325 m (1,066 ft)
  • Numbers of cross passage tubes: 178
  • Maximum overburden:2,450 m (8,040 ft) (at Piz Vatgira)
  • Start of construction: 1993 (sounding drills), 1996 (preparations), 4 November 1999 (official start, first blasting), 2003 (mechanical excavation)
  • Breakthrough: 15 October 2010 (Eastern tube), 23 March 2011 (Western tube)
  • Commissioning: May 2016
  • Inauguration/Opening: 1 June 2016
  • Start of daily passenger service: 11 December 2016 (see public transport timetable#Switzerland)
  • Total cost: CHF 9.74 billion (as of October 2010) (US$10.1 billion)
  • Trains per day: 180–260 freight trains, 50 (65 from 2020) passenger trains
  • Electrification system: 15 kV, 16.7 Hz
  • Maximal speed: 250 kilometres per hour (155.3 mph)
  • Operational speed: Freight trains – minimal 100 km/h (62 mph); Passenger trains – 200 km/h (124 mph)
  • Travel time: Passenger trains – 20 minutes
  • Safety rules: The safety requirements on the rolling stock will be similar to those of other long Swiss tunnels, including the ability for the emergency brake to be overridden.
  • Amount of excavated rock: 28,200,000 t (31,100,000 short tons; 27,800,000 long tons), 13,300,000 m3 or 17,400,000 cu yd, the equivalent of 5 Giza pyramids
  • Number of tunnel boring machines (TBM): Four Herrenknecht Gripper TBMs – Machine numbers S-210 and S-211 operated northbound from Bodio to Faido and Sedrun and were nicknamed Sissi and Heidi respectively; Machines S-229 and S-230 operated southbound from Erstfeld to Sedrun and were known as Gabi I and Gabi II.
  • Total length: 440 m (1,440 ft) (including back-up equipment)
  • Total weight: 3,000 t (3,300 short tons; 3,000 long tons)
  • Power: 5 MW
  • Max. excavation daily: 25–30 m (82–98 ft) (in excellent rock conditions)
  • Total excavation length by TBM: about 45 km (28 mi) (for each tube)
  • Manufacturer: Herrenknecht, Schwanau, Germany
  • References

    Gotthard Base Tunnel Wikipedia


    Similar Topics