The Northern Hub is a rail project in Northern England to improve and increase train services and reduce journey times between its major cities and towns by electrifying lines and removing a major rail bottleneck in Manchester. It is predicted to stimulate economic growth in the region. The project has several elements but the prime objective is to eradicate the bottleneck in Manchester and allow trains to travel through the city at speed without stopping. The project was announced as the Manchester Hub in 2009. The project's steering partnership involves Network Rail, Deutsche Bahn, First TransPennine Express, Northern Rail, East Midlands Trains, CrossCountry, Freightliner, the Department for Transport, Transport for Greater Manchester and Merseytravel.

Contents

Services from Liverpool to Leeds and beyond will be diverted from the Liverpool to Manchester line southern route via Warrington Central and Manchester Piccadilly to the more direct electrified Liverpool to Manchester northern route via Newton-le-Willows and Manchester Victoria, providing a fast route to and through Manchester. The construction of two through platforms at Manchester Piccadilly will allow 4 more trains per hour through the station. The refurbishment of Manchester Victoria station was completed in October 2015 and will become an east-west rail interchange and through station between Liverpool and Leeds. Trains from North East England to Manchester Airport will use the £85 million Ordsall Chord, between Manchester Victoria and Manchester Oxford Road to access Piccadilly and will continue to the airport without reversing at Piccadilly.

The Manchester Hub Study, outlining the project, was released by Network Rail in February 2010. Costs were estimated at £530 million, subsequently reassessed to £560 million. Chancellor George Osborne approved expenditure of £85 million for the Ordsall Chord in his budget on 23 March 2011, and other aspects of the scheme were reviewed to ensure best value. A further £130 million was committed in Osborne's budget of March 2012, and approval for the full scheme was confirmed by the government on 16 July 2012. The first trains are expected to run on the chord in December 2017 and the project will be completed by 2018.

Support for the scheme has been vociferous from civic and business leaders due to the high benefit-to-cost ratio and from politicians such as George Osborne but has been criticised for being incremental and only improving the rail network in Northern England to "where it should have been a decade ago". The scheme has a benefit-to-cost ratio (BCR) of £4 for every £1 invested - double that of Crossrail in London and the proposed High Speed 2 project which have BCRs of £2.10 and £2.30 respectively.

The project may be followed by or merged with High Speed 3. In November 2015 Transport for the North (TfN) proposed a four-track trans-Pennine railway line to link with the HS2 line to London, and a new Liverpool-Manchester airport-Manchester railway line also linked to HS2. A feasibility study of the west to east rail line and its branches into HS2 will be published in March 2016.

Background

The Northern Hub was proposed in February 2010 to resolve problems around Manchester city centre that restricted route capacity and caused delays.

  • Terminating trains in through platforms at Victoria station removed capacity for through trains. The problem could have been mitigated by an additional terminating platform west of the station but operational efficiencies were achieved by altering route paths to relieve congestion.
  • Congestion at Piccadilly was caused by trains having to reverse to travel to Manchester Airport and trains between Liverpool and Yorkshire or the East Midlands had to switch lines across the throat of the station blocking all other services.
  • Freight trains pass through Manchester city centre, unusual for a city centre rail network. Two freight trains per hour pass through Manchester to Trafford Park and no alternative route exists. Freight trains using passenger routes through Manchester was raised in Parliament in 2002.
  • Network Rail concluded that no single intervention would unlock the bottlenecks but that greater efficiency and enhancement to services was possible. A proposal to use Piccadilly primarily for north-south services and Victoria for east-west services was agreed as the most effective course of action.

    The re-alignment of services commenced in May 2014 when First TransPennine Express services between Liverpool and Newcastle were routed through Manchester Victoria rather than Piccadilly. It is expected most TransPennine Express services will pass through Victoria by 2018 after the construction of the Ordsall Chord.

    Station improvements

    Major stations will be improved to include new platforms, station layout re-configuration and redevelopment. Most improvements will be in Manchester aimed at alleviating bottlenecks that delay passing services and restricts routes.

    Manchester

    Victoria station will be re-configured as the Northern England hub for east-west rail services. Once voted the worst station in the United Kingdom, it has received a £44 million transformation including a £20 million roof covering the concourse and four platforms.

    Piccadilly's through platforms, 13 and 14, will be modernised and two through platforms, 15 and 16, will be built over Fairfield Street to alleviate congestion.

    Oxford Road's platforms will be lengthened and a footbridge will be built. The Grade II listed timber grid-shell roof will be incorporated into the new station design. The surrounding site could be redeveloped with office, residential and leisure space.

    Salford Crescent station will be redeveloped at a cost of £12 million and further development could occur should extra capacity be required.

    At Manchester Airport station a new platform will be built creating extra capacity and access for direct services from other cities in Northern England. Construction of the platform began in February 2014. Huyton and Roby stations will have two new tracks through the stations to allow faster trains to pass and provide two additional platforms. Burnley Manchester Road station will receive a £2.3 million upgrade before the reinstatement of a direct rail service to Victoria via the re-opened Todmorden Curve in 2015. Dore and Totley railway station will get a second platform and a footbridge for access. The single track will be doubled.

    Leeds

    At Leeds Station two platforms will be built at a cost of £13.6 million to alleviate congestion.

    Infrastructure

    Northern Hub plans include:

  • Piccadilly and Victoria stations linked by the Ordsall Chord
  • Station improvements completed at Victoria which was rated as the worst station in the United Kingdom in 2009.
  • New platforms at Piccadilly for trains from/to Oxford Road, enabling traffic from the north and west to access the south side.
  • Passing loop between Roby and Huyton on the line from Liverpool to Manchester via Newton-le-Willows,
  • Extra capacity on routes through the Pennines between Leeds, Huddersfield, Dewsbury and Manchester
  • Passing loops at Chinley, Grindleford and Dore between Sheffield and Manchester
  • Electrification

    Electrification for rail lines out of Manchester is underway or has been approved. While independent of the Northern Hub scheme, they complement it:

  • Electrification of the Manchester to Liverpool line was announced by the Department for Transport in July 2009. The section from Manchester to Newton-le-Willows was completed in December 2013 and the section to Liverpool should have been completed by December 2014. The 32-mile line between Liverpool Lime Street and Manchester Victoria via Huyton and Newton Le-Willows has a maximum speed limit of 75 mph. Following electrification and the introduction of Class 319 stock, trains will reach 90 mph cutting journey times from 47 to 32 minutes. The Manchester to Newton-le-Willows section was completed on 17 July 2013, it was marked by a ceremony at Eccles station at which the Secretary of State for Transport, Rt. Hon. Patrick McLoughlin MP, was present. Electrified Manchester to Edinburgh and Glasgow services have been running since the timetable change in December 2013. Due to delays the target date for completion of the section from Earlestown to Liverpool was missed but electric train services between Liverpool and Manchester Airport commenced in March 2015.
  • The Liverpool to Wigan Line is electrified providing a second connection to the West Coast Main Line at Ince Moss Junction via St. Helens Central. The line was operational by May 2015.
  • Electrification of the Manchester to Preston Line via Bolton was announced in December 2009 and is expected to be completed by December 2017. Preparatory work on bridges and tunnels commenced in 2014.
  • Electrification of the line from Preston to Blackpool North was scheduled for completion by May 2016. It joins the Manchester to Preston Line providing an electrified route from Blackpool to Manchester and the West Coast Main Line. This stage is running behind schedule (following a change of engineering contractor and the decision to combine track & signalling alterations with the electrification work) and is unlikely to be finished until 2018.
  • The Huddersfield Line to Leeds and York via Stalybridge was expected to be electrified between 2016 and 2018. Electrification was announced in November 2011, but the plan was halted by the government in 2015 because of rising costs and missed targets. The work is expected to be completed in 2022, after the DfT gave the go-ahead for work to resume in September 2015.
  • Service improvements

    Northern Hub is expected to deliver the following improvements:

  • 14 trains an hour through Manchester compared with 10 currently
  • Up to 700 more trains per day with space for 44 million more people to travel by train each year
  • Two new fast trains per hour between Manchester Victoria and Liverpool Lime Street
  • Six fast trains an hour at peak times between Leeds and Manchester as opposed to five
  • New services to Manchester Airport from Bradford via Halifax, and the Calder Valley and from Chester
  • A 15-minute service to Manchester Airport from Victoria, Oxford Road and Piccadilly
  • An express service between Liverpool Lime Street and Newcastle Central via Manchester Victoria and Leeds commenced in May 2014
  • As part of the Northern Hub scheme; electrification of key lines will enable faster electric trains increasing capacity and lowering journey times. Typically, diesel trains that operated between Manchester and Liverpool such as the Class 142 and Class 156 had a maximum speed limit of 75 mph. Following electrification, Class 319 trains reach a top speed of 100 mph with greater acceleration from stations.

    Network Rail has published target times from Manchester to be achieved after the completion of the Northern Hub projects.

  • Leeds and Manchester target time: 40 minutes - a reduction of 14 minutes
  • Bradford and Manchester target time: 50 minutes - a reduction of 10 minutes
  • Manchester and Sheffield target time: 40 minutes - a reduction of 8 minutes
  • Chester and Manchester target time: 40 minutes - a reduction of 23 minutes
  • Liverpool and Manchester target time: 30 minutes - a reduction of 17 minutes. A reduced journey time of 37 minutes was achieved in May 2014 with the introduction of the new 'express' route and the introduction of Class 319 trains in May 2015 reduced journey times between both cities to 30 minutes.
  • Manchester and Preston target time: 30 minutes - a reduction of 9 minutes
  • There will be faster journey times to the East Midlands via Sheffield, Chester, Halifax, Hull, Newcastle and the North East
  • Timeline

    Network Rail's original aim was for all schemes - including electrification, station upgrades and track work - to be completed by the end of 2018, though this timescale will not be met for the Transpennine electrification.

    2013
  • April - work begins on restoring Manchester Victoria station
  • 30 December - Manchester to West Coast Main Line and Newton-le-Willows electrification complete. New four-carriage Class 350s are introduced, reducing journey times and increasing capacity on the Edinburgh-Manchester Airport route.
  • 2014
  • 20 May - a new fast service between Liverpool and Newcastle via Manchester Victoria begins delivering journey time reductions
  • December - Newton-le-Willows to Liverpool Lime Street and Huyton to Wigan electrification complete - delayed, first services Liverpool to Manchester Airport did not run until March 2015. Four-carriage Class 319s will be introduced increasing capacity between Liverpool and Manchester Airport via Manchester Piccadilly.
  • 2015
  • August - Completion of Manchester Victoria station redevelopment
  • 2016
  • Early 2016 - work begins on building two new platforms at Manchester Piccadilly and re-configuring Manchester Oxford Road (subject to application approval, expected in late 2015)
  • December
  • Manchester Victoria to Preston electrification complete
  • Manchester to Stalybridge electrification complete (TP phase 1)
  • 2017
  • December
  • Ordsall Chord operational
  • Preston-Blackpool electrification complete
  • 2018
  • Platforms 15 and 16 to be operational at Manchester Piccadilly
  • December - Two new platforms at Manchester Piccadilly completed and operational
  • 2022
  • Manchester to Leeds and York electrification is complete
  • Heritage threat

    The historic first passenger railway station, Manchester Liverpool Road, a Grade I listed building, is threatened by the plan. After this project is completed, it will no longer be possible to run trains into or out of the station. The Manchester Museum of Science and Industry management objected to the scheme and an inquiry was set up in 2014 to investigate potential damage to the historic structure.

    Future

    The Northern Hub may be merged into or superseded by a larger project being called High Speed 3. David Higgins, chairman of the HS2, stated in March 2014 that the Northern Hub scheme is incremental and the benefits of the High Speed 2 will not be fully felt if rail links between Northern cities are not improved. In June 2014, George Osborne, Chancellor of the Exchequer stated his vision to see improved transport links between Liverpool, Manchester, Sheffield and Leeds to increase economic productivity. Osborne's proposals were referred to as 'Crossrail of the North' and 'High Speed 3'. In November 2015 Transport for the North (TfN) proposed a four-track trans-Pennine railway line that would link with the HS2 line to London, and a new Liverpool-Manchester airport-Manchester railway line also linked to HS2. A feasibility study of the west to east rail line and its branches into HS2 will be published in March 2016.