Harman Patil (Editor)

Cotter Dam

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Purpose
  
Potable water supply

Type of dam
  
Gravity dam

Height
  
87 m

Impound
  
Cotter River

Status
  
Operational

Impounds
  
Cotter River

Owner
  
Icon Water Limited

Spillway
  
1


Location
  
Australian Capital Territory, Australia

Opening date
  
1912 (1912); 2013 (2013)

Similar
  
Corin Dam, Bendora Dam, Googong Dam, Tidbinbilla Nature Reserve, Mount Stromlo

Cotter dam spilling over for first time since new wall construction


The Cotter Dam is a concrete gravity and rockfill embankment dam across the Cotter River, located in the Australian Capital Territory, Australia. The impounded reservoir is called the Cotter Reservoir which is a supply source of potable water for the city of Canberra and its environs.

Contents

Map of Cotter Dam, Australian Capital Territory, Australia

Enlarged cotter dam flood event march 2012


Original dam completed in 1912

The original concrete gravity Cotter Dam was built in 1912 when the city of Canberra was established. The height of the dam wall was raised to a height of 31 metres (102 ft) in 1951 in order to increase capacity of the reservoir. The 26-thousand-cubic-metre (920×10^3 cu ft) dam wall was 118 metres (387 ft) long and created a reservoir with a surface area of 500 thousand cubic metres (18×10^6 cu ft). The uncontrolled spillway was capable of discharging 850 cubic metres per second (30,000 cu ft/s). At that time, the top water level of the dam was 501 metres (1,644 ft) above sea level and the reservoir had a capacity of 3,856 megalitres (848,000,000 imp gal; 1.019×109 US gal). A subsequent review in October 2006, using more accurate mapping methods, resulted in capacity being re-estimated downwards from the previous estimate of 4,700 megalitres (1.0×109 imp gal; 1.2×109 US gal). Additional galleries and drains were constructed between 1984 and 1986. In order to supply the city with potable water, water from the reservoir was pumped to Mount Stromlo, and from there the water flowed by gravity to fill the city's reservoirs.

The dam water quality had deteriorated compared with Bendora and Corin dams and the dam was only used when water is in short supply. However, in December 2004, ACTEW Corporation brought the dam back on line in response to the ongoing drought.

Enlarged dam completed in 2013

Completed in 2013, the enlarged Cotter Dam comprises a new 87-metre (285 ft) high concrete dam wall built downstream from the old 26-metre (85 ft) high dam wall, along with two auxiliary embankment dam walls along low-lying adjoining valleys. Constructed on rock foundations by Abigroup–John Holland joint venture, with engineering design by GHD, the main dam wall is 330 metres (1,080 ft) long, with the two rockfill embankments 340 metres (1,120 ft) and 300 metres (980 ft) long and 15 metres (49 ft) and 18 metres (59 ft) high respectively, both with internal earthen cores. The enlarged dam walls increased the storage capacity of the Cotter Reservoir from the previous 3.9 gigalitres (860,000,000 imp gal; 1.0×109 US gal) to 78 gigalitres (1.7×1010 imp gal; 2.1×1010 US gal); while the catchment area remains 482 hectares (1,190 acres).

The old dam wall remains, inundated by the water held behind the new dam wall and acting as a sediment trap for the new dam's intake tower. The old dam may only be visible in exceptional circumstances of drought. Completion was originally scheduled for the end of June 2011, however construction was delayed until August 2013 due to heavy rainfalls in the summer of 2010/2011, the discovery of an unexpectedly large rock seam at the site of the foundations in 2011, and severe flooding in March 2012. The uncontrolled spillway is capable of discharging 5,670 cubic metres per second (200,000 cu ft/s) from the 285-hectare (700-acre) Cotter Reservoir, with a high water level approximately 551 metres (1,808 ft) above sea level.

References

Cotter Dam Wikipedia