Purpose
  
Power

Opening date
  
1992

Surface area
  
105 ha

Impound
  
Limia

Status
  
Operational

Address
  
Unnamed Rd, Portugal

Construction began
  
1983

Alto Lindoso Dam

Official name
  
Barragem do Alto Lindoso

Location
  
municipality Ponte da Barca, Viana do Castelo District, Portugal

Owner(s)
  
Companhia Portuguesa de Produção de Electricidade

Similar
  
Castle of Lindoso, Alto Rabagão Dam, Carrapatelo Dam, Peneda‑Gerês National Park, Picote Dam

Intake spherical valve opening sound at alto lindoso dam


Alto Lindoso Dam (Portuguese: Barragem do Alto Lindoso) is a concrete double curvature arch dam on the Lima River. It is located in the municipality Ponte da Barca, in Viana do Castelo District, Portugal. The dam lies in Peneda-Gerês National Park close to the border with Spain.

Contents

Construction of the dam began in 1983. The dam was completed in 1992. It is owned by Companhia Portuguesa de Produção de Electricidade (CPPE). The dam is used for power production.

DamEdit

Alto Lindoso Dam is a 110 m tall (height above foundation) and 297 m long double curvature arch dam with a crest altitude of 339 m. The width at the base is 21 m (crest 4 m). The volume of the dam is 308,500 m³. The dam contains 2 shaft spillways with 3 gates each (combined maximum discharge 2,760 m³/s) and 2 bottom outlets (combined maximum discharge 400 m³/s).

ReservoirEdit

At full reservoir level of 338 m (maximum flood level of 339 m) the reservoir of the dam has a surface area of 1.05 (10.72) km² and its total capacity is 379.01 mio. m³. Its active capacity is 347.91 (270) mio. m³. Minimum operating level is 280 m. With the 347.9 mio. m³ water 224.6 GWh can be produced.

Power plantEdit

The pumped-storage hydroelectric power plant went operational in 1992. It is owned by CPPE, but operated by EDP. The plant has a nameplate capacity of 630 (634) MW. Its average annual generation is 933.8 (909.6, 910 or 948) GWh.

The power station contains 2 Francis turbine-generators with 317 MW (350 MVA) each in an underground powerhouse 340 m below the surface. The turbine rotation is 214.3 rpm. The minimum hydraulic head is 227 m, the maximum 288 m. Maximum flow per turbine is 125 m³/s.

As lower reservoir for Alto Lindoso the reservoir of Touvedo dam is used, which is connected via a tailrace tunnel with a length of 4,883 m.