The Ohio Hub is a high-speed railway project proposed by the Ohio Department of Transportation aimed at revitalizing passenger rail service in the Ohio region. Upon completion, the transit system would be composed of 860 mi (1,380 km) of track serving 32 stations. It would connect four states along with southern Ontario, consisting of 11 major metropolitan areas and 22 million people. The system's goal is to "expand the capacity of the transportation system by improving the railroads for both freight and passenger trains."

Contents

As of 2015, funding for the Ohio Hub project has been withdrawn, though the project has not been officially canceled.

Ohio hub positon at west side transport


Passenger transit

The initial startup cost is currently projected to be in the $500 million range. This does not include the cost of trains or the preparations needed for high-speed service. Currently, two high-speed train systems are being explored. The first, a 79 mph (127 km/h) system, is expected to cost $2.7 billion, or $3.5 million per mile. The second option, a 110 mph (180 km/h) higher-speed system is estimated to cost $3.32 billion, or $4.5 million per mile.

Currently proposed service

The project's hub will be based at Cleveland Hopkins International Airport (the state's largest and busiest airport) with a second Cleveland location near downtown Cleveland, and will provide service to adjacent cities in both the state of Ohio and the Ohio Region. Three proposals have been made for service – a single line system from Cleveland to Cincinnati, and two networked systems with multiple corridors providing service from Cleveland to various cities around the Ohio Region. Each corridor will branch out from Cleveland, and serve from four to nine stations, as well as connections to other regional rail services. Additional lines have been proposed to connect the currently planned corridors with each other throughout the state, as well as to add more stations between major cities.

3-C Corridor

The 3-C Corridor could provide service from Cleveland to Columbus, Dayton, and Cincinnati, a distance of 255 miles (410 km). The service is predicted to carry around 478,000 people a year, using a subsidy of $17 million from the state government.

The proposed corridor has, however, attracted opposition from Republican members of the state board in charge of the project, as the proposed six-hour travel time and 39-mph average speed led the project to be dubbed "snail rail". The service is also opposed by John Kasich, the Republican governor, who had pledged to end the project if elected.

On 24 September 2010, the Federal Railroad Administration authorized the state to spend $15 million of the stimulus money for the purposes of determining specifications and completing studies regarding the corridor. Also on the 24th, the state released a new schedule for the service, which would see three daily round trips being operated, taking slightly over five hours each day, an hour and a half faster than previous estimates.

Following the 2010 gubernatorial elections in Ohio, the newly elected governor John Kasich (Republican) began the process of shutting down the project and returning the money to the federal government. This money will have to be redistributed to other applicants. In a press conference, Kasich said that "[t]hat train is dead. I said it during the campaign. It is dead. Passenger rail is not in Ohio’s future."

On 9 December 2010, US Transportation Secretary Ray LaHood announced that the federal government had revoked the funding for the 3-C corridor, which would be redirected to high-speed rail projects in other states.

Ohio & Lake Erie Regional Rail

The Ohio & Lake Erie Regional Rail will provide service to four states plus Canada through four corridors originating in Cleveland. An additional network has been proposed with three additional lines (seven lines total), however is still under development. The current proposal features the following four corridors:

  • Northwest corridor to Detroit
  • Serves Toledo and Detroit
  • 7 stations total
  • Connects with future Midwest Regional Rail to Chicago, and Via Rail Canada to Montreal and Quebec City
  • Northeast corridor to Toronto
  • Not to be confused with Amtrak's Northeast Corridor between Boston and Washington DC.
  • Serves Erie, Buffalo, Niagara Falls, and Toronto
  • 11 stations total
  • Connects with Empire Corridor to Albany and New York City, and Via Rail Canada to Montreal and Quebec City
  • Southwest corridor to Cincinnati
  • Originally proposed as the 3-C Corridor
  • Serves Columbus, Dayton, and Cincinnati
  • 9 stations total
  • Connects with future Midwest Regional Rail to Indianapolis and Chicago
  • Southeast corridor to Pittsburgh
  • Serves Pittsburgh
  • 4 stations total
  • Connects with Keystone Corridor to Harrisburg and Philadelphia
  • American Recovery and Reinvestment Act of 2009

    On January 28, 2010, the White House announced that Ohio would receive $400 million of its request. This will allow for passenger rail service to return on the 3C corridor.

    On December 9, 2010, the $400 million was reclaimed by the White House, following repeated promises by Governor John Kasich to cancel the project. He attempted to get permission to use the funds on other transportation related projects, but this was rejected by the White House. The money reclaimed was divided among several other states, including California, New York and Florida.

    As of 2015, funding for the Ohio Hub project is on hold, though it has never been officially canceled.