Suvarna Garge (Editor)

Moses Wheeler Bridge

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Crosses
  
Housatonic River

Construction started
  
1955

Opened
  
1958

Body of water
  
Housatonic River

Official name
  
Moses Wheeler Bridge

Total length
  
967 m

Bridge type
  
Girder bridge

Location
  
Milford, Stratford

Moses Wheeler Bridge

Carries
  
6 lanes of I-95 / Conn. Turnpike

Locale
  
Stratford, Connecticut/Milford, Connecticut

Maintained by
  
Connecticut Department of Transportation

Design
  
Continuous steel plate girder and floorbeam

Address
  
Governor John Davis Lodge Turnpike, Milford, CT 06461, USA

Similar
  
West River Bridge, Park Avenue Viaduct, Igor I Sikorsky Memorial, Washington Bridge, Pearl Harbor Memorial

Moses Wheeler Bridge carries Interstate 95 (Connecticut Turnpike) over the Housatonic River between Stratford and the Devon section of Milford. The current bridge is a 14-span continuous girder and floorbeam structure that carries three (expandable to four) lanes of traffic in each direction, with full inside and outside shoulders. The current bridge, to be completed in 2016, replaces a pre-existing structure that was completed as part of the original Connecticut Turnpike in 1958. The original bridge was a 34-span plate girder structure with a concrete deck with three 12-foot travel lanes in each direction and no shoulders. The central span of the original bridge over the river's navigation channel included a pin and hanger assembly, which are no longer used in bridge construction. Construction on the Moses Wheeler Bridge began in 1955 and opened on January 2, 1958.

Contents

Possible flaw in moses wheeler bridge puts project over budget sets back completion


Ongoing replacement

Heavy traffic and harsh New England weather have taken their toll on the Moses Wheeler Bridge. It has been rated as 'structurally deficient' during recent inspections, with accelerating deterioration of the structural steel being of particular concern. The Connecticut Department of Transportation (CONNDOT) began drawing up plans to replace the bridge in 1996. Originally CONNDOT planned to construct the new bridge to the south of the existing one, away from 115 kilovolt high tension wires that run atop the nearby Metro-North Railroad Drawridge. Stratford residents and officials demanded the new bridge be built to the north of the existing span, closer to the Metro-North bridge and the power lines. A compromise was reached where the new bridge will use approximately the same alignment as the existing one, though be substantially wider. To make this possible, the project will be completed in three stages: the first two stages will consist of constructing the outer parts of the new bridge that will eventually carry two outer lanes and the outer shoulder, while three lanes of traffic are maintained on the existing bridge. During the final stage of construction, three lanes of traffic will be shifted to the new outer spans, at which point crews will demolish the existing span and complete the center portion of the new bridge.

The new bridge will accommodate six lanes (expandable to eight with restriping) of traffic with full left and right shoulders. Two design options were developed for the new 14-span structure: one option using segmented concrete hollow box girders, and the other using continuous steel plate girders. The bridge is designed for seismic loading to withstand a major earthquake. Additionally, it will include a fender system to protect the bridge piers from ship collisions. Aesthetic features are also included, among which is encasing the bridge piers with decorative granite and aesthetic lighting. The STV Group designed the replacement bridge. The existing bridge has no shoulders.

Environmental studies for the new bridge were completed in 2005, and CONNDOT awarded a $60 million contract to Torrington, Connecticut-based O&G Industries for the initial phase of work in July 2009. Construction on the first phase of replacing the bridge, including the foundations for the new bridge piers and temporary work trusses in the Housatonic River began in September 2009. The $166.5 million contract that will build the remainder of the new bridge and demolish the existing span was awarded to a joint venture between Chicago, Illinois-based Walsh Construction Company and Denver, Colorado-based PCL Constructors (also referred to in contract documents as Walsh/PCL Joint Venture II) in August 2011, and will pursue the option using the continuous steel plate girder design.

Walsh/PCL commenced work to widen I-95 on the east and west approaches and began erecting the bridge piers for the new Moses Wheeler Bridge in September 2011. Crews shifted I-95 traffic to the southern half of the roadway so the northern half of the highway, including several smaller overspasses could rebuilt and expanded. On January 17, 2013, southbound traffic was shifted onto the completed northern third of the new bridge and approaches. Northbound traffic was shifted onto the former southbound lanes of the old bridge on January 26, 2013. The Walsh-PCL contrsuction team began demolishing the northbound portion of the old bridge and approaches in February 2013. Demolition of the old northbound span was completed in May 2013, and crews began erecting structural steel for the new northbound lanes in June 2013. In December 2013, northbound traffic was shifted from the old bridge to the new northbound lanes, at which point the remainder of the original 1958 structure was taken out of service and removed. During the summer of 2014, three large gantry cranes were assembled in the median of I-95 to enable construction of the center portion of the new span. By the end of 2015,construction of the new Moses Wheeler Bridge is expected to reach substantial completion, with final paving and striping scheduled for 2016.

Emergency repairs

During the summer of 2007, CONNDOT performed a $6.9 million emergency repair project to the Moses Wheeler Bridge after several large holes opened up in the bridge deck, and advanced deterioration of the structural steel was discovered during a routine inspection. The project involved a full-depth patch and repair of the bridge deck, roadway resurfacing, and reinforcement of key superstructure components to ensure the bridge could remain in service until the new bridge can be built.

References

Moses Wheeler Bridge Wikipedia