Country
  
Commissioned
  
1985

Power rating
  
5,500 MW (original)

Construction started
  
1980

From
  
Total length
  
432 km (268 mi)

Operator
  
Type of current
  
Alternating current

Ekibastuz–Kokshetau high-voltage line httpsuploadwikimediaorgwikipediacommonsthu

AC Voltage
  
1,150 kV (original)500 kV (current)

Similar
  
Ekibastuz GRES‑2 Power St, Ekibastuz GRES‑1, Arkhangelskoye Palace, Sayano–Shushenskaya Dam

The Ekibastuz–Kokshetau high-voltage line is an alternating current electrical power transmission line in Kazakhstan from Ekibastuz to Kokshetau. It was the first commercially used power line in the world which operated at 1,150 kV, the highest transmission line voltage in the world. It is a part of the Itatsk (Sharypovo)–Barnaul–Ekibastuz–KokshetauKostanayChelyabinsk (Siberia–Kazakhstan–Urals) transmission system, which was designed to transfer electricity from Siberia and Kazakhstan to industrial region in Urals.

Designated as power line number 1101, it runs 432 kilometres (268 mi) from Ekibastuz to Kokshetau. It is mounted on transmission towers with an average height of 45 metres (148 ft). The weight of the conductors between the spans is approximately 50 tons. With a voltage of 1,150 kV the line had a maximum transfer capacity of 5,500 MW.

The whole length of the Siberia–Kazakhstan–Urals line is 2,344 kilometres (1,456 mi), of which 1,421 kilometres (883 mi) is located in Kazakhstan and the rest is located in Russia.

History

In 1973, the Soviet Union built a three-phase UHV experimental test circuit over a kilometre long at the Beily Rast substation, near Dmitrov in Moscow region. In 1978, a 270 km UHV test line for industrial use was built from Sharypovo to Novokuznetsk. In 1985, this test line became part of the Siberia–Urals line. At the time, no other country had an operational UHV line of this voltage, although several other countries were running experiments.

On 24 March 1977, the Central Committee of the Communist Party of the Soviet Union and the Council of Ministers of the Soviet Union took a decision of construction of the Ekibastuz–Centre (Tambov) 1,500 kV direct current line. This line was under construction but was never finished. In addition, the Ekibastuz–Urals line was planned. Construction of this line started in 1980. The Ekibastuz–Kokshetau line was commissioned in the end of July 1985. The technical design of the line was done by Energosetproekt. The main contractor was Specsetstroy, while contractors for the 1,150 kV substations were Ekibastuzenergostroy and Yuzhuralenergostroy. Equipment for substations were provided by Zaporozhtransformator, Elektrosila, and Uralelektrotyazhmash.

In 1988, this 1,150 kV line was prolonged to Kostanay. By 1990, the whole line from Barnaul to Chelyabinsk was built; however, as 1,150 kV substations were built only in the territory of Kazakhstan, the rest of this system operated at 500 kV. After dissolution of the Soviet Union in 1991, the whole Siberia–Urals transmission system was downgraded to 500 kV. In 1998, the Siberia–Urals line was prolonged from Barnaul to Itatsk.

References