Harman Patil (Editor)

Dudgeon Offshore Wind Farm

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Status
  
Under construction

Type
  
Offshore

Units operational
  
67

Commission date
  
2017 (2017)

Distance from shore
  
32 km (20 mi)

Dudgeon Offshore Wind Farm voiceofrenewablescomwpcontentuploads201605D

Country
  
England, United Kingdom

Location
  
32km north of Cromer, Norfolk

Owners
  
Statoil, Masdar, Statkraft

Dudgeon Offshore Wind Farm is an offshore wind farm being developed 32 km north of Cromer off the coast of Norfolk, in the North Sea, England. It is owned by Dudgeon Offshore Wind Limited (DOW), a subsidiary of Statoil, Masdar and Statkraft. The site is a relatively flat area of seabed between the Cromer Knoll and Inner Cromer Knoll sandbanks and is one of the furthest offshore sites currently being developed around the UK.

Contents

Dudgeon Offshore Wind Farm First electricity delivered from Dudgeon Offshore Wind Farm REVE

The project includes constructing the wind turbines and their foundations, building an offshore substation and an onshore substation at Necton, installing power cables both undersea and onshore, as well as connection to the UK National Grid. This work is estimated to take about two years and cost in the region of £1.5bn. The wind farm should be fully operational by the end of 2017.

Dudgeon Offshore Wind Farm Dudgeon Offshore Wind Farm

Planning

Dudgeon Offshore Wind Farm Green light for Dudgeon Offshore Wind Farm Statkraft

The project was originally developed by Warwick Energy Limited, who set up a subsidiary called Dudgeon Offshore Wind Limited. The wind farm planning application was filed in April 2009. The application was for between 56 and 168 turbines depending on final chosen design with a nameplate capacity of 560 MW.

Dudgeon Offshore Wind Farm Green light for Dudgeon Offshore Wind Farm Statkraft

In July 2012 the government gave planning approval for Warwick Energy to construct a wind farm to the capacity of 560MW. In October 2012 Statoil and Statkraft acquired the Dudgeon Offshore Wind Farm project through the acquisition of all shares from Warwick Energy. A review of the project was undertaken after the project was acquired by Statoil and Statkraft, and in December 2013 it was announced that the capacity of the wind farm would be reduced from 560MW to 402MW.

Dudgeon Offshore Wind Farm Windfarm Update Dudgeon Offshore Wind

In January 2014 it was announced that two contracts had been awarded to Siemens for the engineering, supply, assembly, commissioning and service of 67 6MW wind turbines for the project. Statoil and Statkraft made the final investment decision on 1 July 2014 and announced that they would proceed with the project.

Dudgeon Offshore Wind Farm Dudgeon Offshore Wind Farm Bringing the power to shore

In September 2014 it was announced that Masdar had purchased 35%, half of Statoil's shares, of Dudgeon Offshore Wind Limited. Statoil now holds a 35% share, Masdar a 35% share and Statkraft a 30% share in Dudgeon Offshore Wind Limited.

Construction

Work began onshore in Norfolk to install the underground cables and construct the substations on March 26, 2015. The turbine foundations were laid in 2016, with turbine installation occurring in 2017, the first coming on line in early February 2017.

Final commissioning is planned for the end of 2017.

References

Dudgeon Offshore Wind Farm Wikipedia