Official name
  
Yusufeli Baraji

Status
  
Under construction

Height
  
270 m

Owner
  
State Hydraulic Works

Impound
  
Çoruh River

Country
  
Turkey

Opening date
  
May 2018 est.

Surface area
  
33 km²

Construction began
  
26 February 2013

Yusufeli Dam wwwkolincomtrenglishimagesprojectsgalleryl

Location
  
Yusufeli, Artvin Province

Construction cost
  
487 million (approx. US$270 million)

Similar
  
Çoruh River, Deriner Dam, Borçka Dam, Ilısu Dam, Muratlı Dam

The Yusufeli Dam is an arch dam under construction on the Çoruh River near Yusufeli in Artvin Province within the eastern Black Sea region of Turkey. The Yusufeli Dam will be the second largest dam within the larger Çoruh River Development Plan, which plans to build 13 dams, of which two are operational and another two are under construction. The dam's main purpose is hydroelectric power production and it will support a 540 MW power station. The dam is controversial because of its projected impact on the biodiversity within its reservoir area along with the relocation of locals.

Contents

Map of Yusufeli Dam, 08890 Sebzeciler K%C3%B6y%C3%BC%2FYusufeli%2FArtvin, Turkey

On February 26, 2013, the foundation stone was laid in a ceremony attended by Minister of Forestry and Waterworks Veysel Eroğlu and Minister of Labor and Social Security Faruk Çelik. It is expected that the construction of the dam will cost 487 million (approx. US$270 million). The dam's opening date is set to May 29, 2018. When completed, Yusufeli Dam will be Turkey's highest.

History

The first studies on the Yusufeli Dam were carried out in the 1970s and it was included in the Coruh River Hydropower Development Master Plan in 1982. The feasibility report was completed in 1986 and the project was added to the national plan in 1997.

Design

Situated 70 km (43 mi) southwest of Artvin, the Yusufeli will be a double-curvature arch dam with a height of 270 m (886 ft) from its foundation and 223 m (732 ft) from the river's thalweg (lowest point of river bed). It will have a crest length of 490 m (1,608 ft) and crest width of 15 m (49 ft) while being composed of 2,900,000 m3 (102,412,533 cu ft) of concrete.

The dam's crest will sit at an altitude of 715 m (2,346 ft) above sea level while the normal operating level of its reservoir will be 710 m (2,329 ft), maximum will be 712 m (2,336 ft) and the minimum 670 m (2,198 ft). The reservoir surface area of 33 km2 (13 sq mi) will have a total storage capacity of 2,130,000,000 m3 (1,726,819 acre·ft) and an active or "useful" storage of 1,080,000,000 m3 (875,570 acre·ft). The dam's spillway will be a service controlled chute type with a maximum discharge capacity of 8,000 m3/s (282,517 cu ft/s).

The dam will have an underground power station that is 110 m (361 ft) long, 21.4 m (70 ft) wide and 45.2 m (148 ft) high. Within the power station will be 3 x 180 MW vertical shaft Francis turbines.

Design activities will be carried out by Su-Yapi Engineering and Consulting Inc.

Construction is to be carried out by a Limak Holding-Cengiz Holding-Kolin consortium.

Projected biological impacts

If built, the Yusufeli Dam will is expect to have significant biological impacts including:

  • Adversely affecting 21 nationally listed threatened plant species, (including Iris taochia) of which all except one are endemic to Turkey. Of these threatened species 2 taxa are limited to Yusufeli and its surroundings, 8 are limited to the Çoruh Valley, and 6 to the Artvin-Erzurum area. Turkish Red Book for Plants shows that of these, 7 species are critically endangered, 5 are endangered and 9 are vulnerable.
  • Adversely affecting 12 nationally listed threatened mammal species including the; wild goat (Capra aegagrus), chamois (Rupicapra rupicapra), Persian squirrel (Sciurus anomalus), forest dormouse (Dryomys nitedula), brown bear (Ursus arctos), Eurasian badger (Meles meles), gray wolf (Canis lupus), Mediterranean horseshoe bat (Rhinolophus euryale), lesser horseshoe bat (Rhinolophus hipposideros), greater mouse-eared bat (Myotis myotis), Schreibers’ bat (Miniopterus schreibersii) and pipistrelle bat (Pipistrellus pipistrellus). Of these species the Mediterranean bat and wild goat are internationally listed on IUCN Red List of Threatened Species.
  • Adversely affecting 2 nationally threatened fish species, the Black Sea salmon (Salmo trutta labrax) and brown trout (Salmo trutta macrostigma). The Black Sea salmon’s migration will be blocked because of this and the other planned and built dams. Existing populations of fish will be adversely affected by the construction of the dam and another 6 species populations may not recover due to the reduction of creek and river habitat needed for breeding.
  • Potentially adversely affecting 5 butterfly and 1 dragonfly regionally rare species (Polyommatus poseidon, Pseudophilotes vicrama, Pyrgus cirsii, Scolitantides orion, Thymelicus acteon, and Onychogomphus assimilis) of which 2 are listed in the IUCN Red List Pyrgus cirsii and Onychogomphus assimilis.
  • References