Status Under construction Height 270 m Owner State Hydraulic Works Impound Çoruh River | Opening date May 2018 est. Surface area 33 km² Construction began 26 February 2013 | |
![]() | ||
Construction cost 487 million (approx. US$270 million) Similar Çoruh River, Deriner Dam, Borçka Dam, Ilısu Dam, Muratlı Dam |
The Yusufeli Dam is an arch dam under construction on the Çoruh River near Yusufeli in Artvin Province within the eastern Black Sea region of Turkey. The Yusufeli Dam will be the second largest dam within the larger Çoruh River Development Plan, which plans to build 13 dams, of which two are operational and another two are under construction. The dam's main purpose is hydroelectric power production and it will support a 540 MW power station. The dam is controversial because of its projected impact on the biodiversity within its reservoir area along with the relocation of locals.
Contents
- Map of Yusufeli Dam 08890 Sebzeciler KC3B6yC3BC2FYusufeli2FArtvin Turkey
- History
- Design
- Projected biological impacts
- References
Map of Yusufeli Dam, 08890 Sebzeciler K%C3%B6y%C3%BC%2FYusufeli%2FArtvin, Turkey
On February 26, 2013, the foundation stone was laid in a ceremony attended by Minister of Forestry and Waterworks Veysel Eroğlu and Minister of Labor and Social Security Faruk Çelik. It is expected that the construction of the dam will cost 487 million (approx. US$270 million). The dam's opening date is set to May 29, 2018. When completed, Yusufeli Dam will be Turkey's highest.
History
The first studies on the Yusufeli Dam were carried out in the 1970s and it was included in the Coruh River Hydropower Development Master Plan in 1982. The feasibility report was completed in 1986 and the project was added to the national plan in 1997.
Design
Situated 70 km (43 mi) southwest of Artvin, the Yusufeli will be a double-curvature arch dam with a height of 270 m (886 ft) from its foundation and 223 m (732 ft) from the river's thalweg (lowest point of river bed). It will have a crest length of 490 m (1,608 ft) and crest width of 15 m (49 ft) while being composed of 2,900,000 m3 (102,412,533 cu ft) of concrete.
The dam's crest will sit at an altitude of 715 m (2,346 ft) above sea level while the normal operating level of its reservoir will be 710 m (2,329 ft), maximum will be 712 m (2,336 ft) and the minimum 670 m (2,198 ft). The reservoir surface area of 33 km2 (13 sq mi) will have a total storage capacity of 2,130,000,000 m3 (1,726,819 acre·ft) and an active or "useful" storage of 1,080,000,000 m3 (875,570 acre·ft). The dam's spillway will be a service controlled chute type with a maximum discharge capacity of 8,000 m3/s (282,517 cu ft/s).
The dam will have an underground power station that is 110 m (361 ft) long, 21.4 m (70 ft) wide and 45.2 m (148 ft) high. Within the power station will be 3 x 180 MW vertical shaft Francis turbines.
Design activities will be carried out by Su-Yapi Engineering and Consulting Inc.
Construction is to be carried out by a Limak Holding-Cengiz Holding-Kolin consortium.
Projected biological impacts
If built, the Yusufeli Dam will is expect to have significant biological impacts including: