Supriya Ghosh (Editor)

Walney Wind Farm

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Status
  
Operational

Rotor diameter
  
120 m

Site area
  
73 km²

Nameplate capacity
  
367

Distance from shore
  
15 km (9 mi)

Type
  
Offshore

Capacity factor
  
43%

Construction began
  
March 2010

Commission date
  
February 2012

Units operational
  
102 × 3.6 MW

Walney Wind Farm Walney offshore wind farm in double size plan BBC News

Country
  
England, United Kingdom

Make and model
  
Siemens Wind Power: SWT-3.6

Location
  
14km west of Walney Island off the coast of Cumbria

Brattbergs and bellmouths the walney wind farm song


Walney Wind Farm is an offshore wind farm 14 km west of Walney Island off the coast of Cumbria, in the Irish Sea, England. It has a capacity of 367 MW, which makes it one of the world's largest offshore wind farms. The wind farm was developed by Walney (UK) Offshore Windfarms Limited, a partnership between DONG Energy and Scottish and Southern Energy. The farm is immediately north west of the West of Duddon Sands Wind Farm and also to the west of Ormonde Wind Farm. The farm is in water depths ranging from 19m to 23m and covers an area of approximately 73 km2.

Contents

Walney Wind Farm Walney Offshore Wind

Walney wind farm from isle of man


Description

Walney Wind Farm Maritime Journal UK Consent for Walney Wind Farm

Both phases have 51 turbines giving a nameplate capacity of 367 MW. Until September 2012 it was the world's largest operational offshore wind farm. It is expected to generate about 1,300 GW·h/year of electricity, with a load factor of 43%.

Construction

Walney Wind Farm Walney Offshore Wind Farm To Triple In Size CleanTechnica

In 2004 DONG Energy was awarded a 50-year lease from The Crown Estate to develop a wind farm off Walney Island, as part of the second UK offshore wind farm tendering process known as "Round 2". The farm was constructed sequentially in two phases with overlapping installation activities to reduce the overall construction timeframe.

Walney Wind Farm httpsuploadwikimediaorgwikipediacommonsthu

The project involved constructing the wind turbines and their foundations, building two offshore substations and installing two undersea power cables, one for each phase, and two short onshore cables to connect to two existing onshore Electrical substations for connection into the UK National Grid. A cable was laid by Stemat Spirit. Phase 1 connects to a substation at Heysham and Phase 2 connects to substation at Stanah, south of Fleetwood. Both undersea cables pass close by Barrow Wind Farm. All the construction work was expected to take less than 2 years, with both phases operational by the end of 2011. On 11 July 2011 Phase 1 became operational, comprising 51 turbines with an installed capacity of 183.6MW.

Walney Wind Farm offshore wind farm is worlds biggest for now

Walney 2 began sending power to the grid on 1 November 2011. In February 2012, DONG Energy claimed to have installed the 51 turbines in Walney 2 in 5 months and 14 days, including monopiles and complete turbines; about 3.25 days per turbine. Walney 1 took 7 months. The improvement is due to commonality of projects and resources. The wind farm was officially opened on 9 February 2012 by the new energy secretary, Ed Davey, MP, although the last of the 51 turbines in Walney 2 were only activated in April 2012.

Walney Extension

Walney Wind Farm PGGM Ampere Refinance Walney OWF Debt Offshore Wind

In November 2014 DONG Energy was given development consent for an extension to the Walney offshore wind farm. The development consent allowed a maximum of 207 turbines to be added to the existing 102 turbines. The maximum generating capacity of the extension was said to be 750MW although DONG was reported to be proceeding with a project based around 660MW. Construction is expected to begin in 2017. In 2015 DONG chose the 8MW Vestas V164 for Phase 1, and the 7MW Siemens gearless turbine for Phase 2.

Involvement in oil spill

In 2014 a dive vessel, owned by Danish firm Offshore Marine Services, was carrying out routine inspection work when an anchor cable broke and the ship slammed into one of 102 turbines installed at the Walney Offshore Wind Farm. The UK’s Maritime and Coastguard Agency surveyed the crash site and reported that a surface sheen stretching 33 feet wide and 0.7 nautical miles long was trailing the vessel. The agency said that, unlike heavier crude oil, the marine engine oil should evaporate or disperse naturally.

References

Walney Wind Farm Wikipedia


Similar Topics