Puneet Varma (Editor)

Race Bank wind farm

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Status
  
consented

Max. water depth
  
26 m

Type
  
Offshore

Distance from shore
  
32 km

Race Bank wind farm httpsmedialicdncommprmprAAEAAQAAAAAAAAS9AA

Country
  
England, United Kingdom

Location
  
27 km off the coast of north Norfolk

Race Bank Wind Farm is a proposed 580 MW Round 2 offshore wind farm located 27 km north of Blakeney Point off the coast of Norfolk, and 28 km east of Chapel St Leonards off the Lincolnshire coast in the North Sea.

Contents

Race Bank wind farm DONG Energy39s Race Bank offshore wind farm is a 580MW project being

Planning

Race Bank wind farm First Race Bank Offshore Substation In Place Offshore Wind

In 2002 the UK government designated the Greater Wash strategic area as potential offshore wind farm development region. In 2004, Centrica was awarded a lease by The Crown Estate during the Round 2 wind farm leasing process to develop a wind farm on Race Bank. The wind farm site was located on a sandbank approximately 27 kilometres (17 mi) north of the north Norfolk coast, and 28 kilometres (17 mi) east of the Lincolnshire coast, with an estimated maximum capacity of 620 MW. The scheme was developed in association with AMEC and the RES Group. The wind farm was to connect to the National Grid at Walpole, together with two of Centrica's other Round 2 wind farms, Lincs Wind Farm and Docking Shoal Wind Farm.

Race Bank wind farm Milestone moment as the first foundation is installed at Race Bank

In 2009 Centrica submitted a planning consent application for a wind farm of up 620 MW capacity. The proposed wind farm covered an area of 75 square kilometres (29 sq mi) at water depths of 4 to 22 metres (13 to 72 ft).

Race Bank wind farm Dong Energy Browsing Locations for Race Bank Construction Base

In July 2012 the government gave planning approval for Centrica to construct a wind farm to the capacity of 580 MW.

Race Bank wind farm DONG Energy Race Bank Wind Farm ROV Inspection and EOD Project

In November 2013 the project failed to be shortlisted for early contract for difference subsidies from the Department of Energy and Climate Change, putting the future of the project in doubt; in December 2013, Centrica sold the project to DONG Energy for £50 million.

Race Bank wind farm Race Bank Offshore Wind Farm Power Technology

As of May 2014, Dong Energy estimated that onshore construction will begin in spring 2015 at the earliest, followed by offshore construction in spring 2016.

In late 2014 DONG Energy applied for a variation of the original (2009) planning consent, substituting two larger offshore substations for the three originally consented. The new substations were to use improved technology and export electrical power at up to 220kV AC. The new substations were to be supported on four-legged jacket foundations secured to the sea floor with pin piles; as a consequence of the change the number of export cables was to be reduced to two. The Department of Energy and Climate Change consented the changes in March 2015.

In June 2014 Dong committed to building the wind farm, which was to receive subsidies under the Renewables Obligation scheme (1.8 ROCs per MWh).

Construction

Contracts for the construction were let from 2015: Turnkey supply and installation of electrical equipment for the STATCOM for the farm was awarded to RXPE (China); NKT (Cologne) was awarded the contract for the 220kV export cables; the 36kV inter array cabling supply was contracted to JDR (Hartlepool); steel foundations to Bilfinger subsidiary Bilfinger Mars Offshore; and an order for 91 6 MW 154 m Siemens Wind turbines was confirmed in mid-2015.

The turbines will be installed in waters of depth 6 to 26 metres (20 to 85 ft).

In July 2015 MMT was contracted to clear the cable route of possible unexploded ordnance. Over 40 second world war bombs were located along the cable export route, which were either removed or destroyed in situ.

The first monopile foundation was installed by July 2016.

References

Race Bank wind farm Wikipedia