Official name 國聖核能發電廠 Location Wanli, New Taipei Phone +886 2 2498 6353 | Country Republic of China Status Operational Owner Taiwan Power Company | |
![]() | ||
Commission date December 1981 (Unit 1)
March 1983 (Unit 2) Decommission date 2021 (Unit 1) - Planned
2023 (Unit 2) - Planned Address 207, Taiwan, New Taipei City, Wanli District, 野柳里八斗60號 Hours Open today · 8:20AM–4:20PMSunday8:20AM–4:20PMMonday8:20AM–4:20PMTuesdayClosedWednesday8:20AM–4:20PMThursday8:20AM–4:20PMFriday8:20AM–4:20PMSaturday8:20AM–4:20PM Similar 台電北部展示館, Yehliu Geopark, Queen's Head, Jinshan Old Street, 台電第二核能發電廠停車場 |
The Kuosheng Nuclear Power Plant or Guosheng Nuclear Power Plant (國聖核能發電廠 or 核二) is a nuclear power plant in Wanli, New Taipei, Taiwan. The plant is currently the largest nuclear power plant in Taiwan, before the opening of the 2,700 MW Longmen Nuclear Power Plant which is still under construction.
Contents
As of 2015, more than 5 million people live within 30 km of the NPP, second only to KANUPP in Pakistan.
Generation
The power plant can generate 16 billion kWh of electricity per year.
2010
On 7 October 2010, the Unit 1 of the plant was shutdown for refueling starting at 12:49 a.m. and was synchronized back to the system on 31 October at 12:14 p.m., setting a record breaking among all existing nuclear power plants in Taiwan for the shortest overhaul duration of 24.48 days.
2011
On 17 May 2011, Taiwan held its very first compounded nuclear disaster drill at the power plant organized by Taipower and New Taipei City Fire Department witnessed by President Ma Ying-jeou. The training scenario is based on Fukushima Daiichi nuclear disaster on 11 March 2011. A statement made by Taipower in the worst-case scenario of a total power failure of the plant, they would make life saving as the top priority by abandoning the plant and injecting seawater to prevent the meltdown of the nuclear core.
2012
During a routine maintenance of the power plant on 16 March 2012, the plant maintenance workers discovered problems on the seven anchor bolts used to secure the bottom of the nuclear reactor to the steel-reinforced concrete substrate that holds the weight of the reactor. One bolt was broken, two were fractured and four were cracked. Taipower said that they would consult other related agencies to analyze and fix the problem and add vibration monitoring sensor near the supporting base of the reactor for continuous monitoring.
2013
The first nuclear reactor of the plant automatically shut down on Friday, 21 June 2013. The event was triggered by protective device activated by the grounding signal of the generator. The signal occurred when the blade of the air damper became loose and fell into busbar between the generator and main transformer. The incident did not damage the reactor and there was no release of radioactivity. Mitigation actions taken by Taipower were done by resecuring the blade and replacing the related components. The power plant was back online on Sunday, 23 June 2013.
2015
On 26 December 2015. the reactor number one of the power plant shut down unexpectedly due to a problem with its control systems.
2016
On 16 May 2016, the reactor number two of the power plant was suspended due to sudden unexpected shut down. The incident occurred after being resumed to work after undergoing annual maintenance for a month.
On 30 May 2016, one of the reactor of the power plant suddenly shut down.
Awards
On 3 November 2010, the 360 Degrees Work Platform over Reactor project of the plant was awarded gold medal as the Best Operation and Maintenance Project during the 6th 2010 Asia Power Awards in Singapore, organized by Asia Power magazine.