Harman Patil (Editor)

Itumbiara Dam

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Official name
  
Usina de Itumbiara

Construction cost
  
$716 million USD

Impounds
  
Paranaíba River

Operator
  
Eletrobras Furnas

Impound
  
Paranaíba River

Opening date
  
1980

Type of dam
  
Embankment

Opened
  
1980

Construction began
  
1974

Turbine
  
6

Itumbiara Dam httpsuploadwikimediaorgwikipediacommonsthu

Location
  
Itumbiara, Goiás, Brazil

Similar
  
Marimbondo Dam, Água Vermelha Dam, Peixotos Dam, Ilha Solteira Dam, Manso Dam

The Itumbiara Dam is an embankment dam on the Paranaíba River near Itumbiara in Goiás, Brazil. The dam serves an associated hydroelectric power plant with a 2,082 megawatts (2,792,000 hp) installed capacity. The power plant is the sixth largest in Brazil and has the largest installed capacity of Eletrobrás Furnas' power plants.

Contents

Map of Itumbiara Dam, Arapor%C3%A3 - MG, Brazil

Background

Between 1963 and 1965, a consortium of U.S., Canadian and Brazilian engineering firms studied and selected sites in Brazil for dams that would assist in developing the region with electricity. Originally, the Itumbiara Dam was to have a shorter height which would accommodate two other dams upstream. A change in plans raised the height of the dam, increasing the reservoir, eliminating the need for the two dams upstream and doubling power production.

Construction

Construction on the dam and power plant began in November 1974 and the river was diverted by September 1, 1976. On October 1, 1979, the reservoir behind the dam began to fill and on September 30, 1979, the left embankment was complete while the right was on November 30 of that same year. The whole dam was completed in April 1980. Despite poor weather along with engineering and technical difficulties, the project was completed on time. 97% of the firms working on the project were Brazilian and 90% of the supplies provided for construction were from Brazil. The dam and power plant was originally estimated to cost $439 million but ended over $716 million when construction was complete. Including the electrical transmission system, the whole project cost just over $1 billion. $125 million for construction was financed by the World Bank.

Itumbiara Hydroelectric Power Plant

On April 27, 1980, the first generator went online and the last on December 30, 1981 just two weeks after the power house was complete. In 1997, the controls for the plant were switched to remote operation in a central plant in Corumba, leaving the control room unmanned. The power house is 25 m (82 ft) wide and 223 m (732 ft) long and contains six 347 MW generators that are powered by Francis turbines.

Specifications

The Itumbiara Dam is a 7,000 metres (23,000 ft) long and 106 metres (348 ft) high earth-fill embankment dam with a concrete spillway and power house section. The earthen portion of the dam contains 31,500,000 cubic metres (1.11×109 cu ft) of earth fill while the concrete portion contains 1,800,000 cubic metres (64,000,000 cu ft) for a total structural volume of 33,300,000 cubic metres (1.18×109 cu ft). The dam's spillway contains six floodgates that are 15 metres (49 ft) wide and 9 metres (30 ft) high each. In total, the spillway has a 16,000 cubic metres per second (570,000 cu ft/s) discharge capacity.