Trisha Shetty (Editor)

Electricity sector in Iraq

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Electricity sector in Iraq

As of June 2013, the output of electricity sector in Iraq averages more than 10,000 MW, while the demand is typically more than 14,000 MW. As of January 2016, the figures are output of 13,000 MW and demand of 21,000 MW. In 2006, the average peak electricity supply was 4,280 MW falling short of demand averaged 8,180 MW by about 3,950 MW. According to U.S. agency officials, demand for electricity has been stimulated by a growing economy and a surge in consumer purchases of appliances and electronics. In addition, electricity is subsidized in Iraq, which leads to increased demand.

Contents

Infrastructure

Iraq's electricity infrastructure consists of a network of

  • Generation facilities that produce power
  • Transmission stations and lines that transmit power from power stations to distribution networks
  • Distribution stations and lines that move power to the end users
  • An automated monitoring and control system, under development, which is a centralized communications and control system designed to monitor system performance and control equitable distribution of power.
  • History

    Electricity entered Iraq for the first time in 1917 where the first electric machine was installed in "Khan Dala" building.

    1990

    Prior to the Gulf War, the total installed generating capacity was 9,295 MW with a peak demand of about 5,100 MW. Approximately 87% of the population had access to electricity. A combination of wars, sanctions, looting and vandalism has however, severely affected the entire power system infrastructure in Iraq.

    1991-2003

    During the 1991 Gulf War the electricity system suffered severe damage. Several transmission lines were put out of service, substations were damaged. While some of the damage of the 1991 war was repaired and about 4,500 MW of generating capacity was available in 1999 when Iraq reorganized its electricity sector. The sector was separated from the Ministry of Industry, and the Commission of Electricity (CoE) was established on June 21, 1999. About 4500 MW of generating capacity became available by the end of 2002, power supply remained insufficient and unreliable. Programmed load shedding and unplanned power outages were frequent.

    Post 2003 war

    Although the power system was not significantly affected by the last conflict, capacity was reduced to approximately 3,300 MW by a combination of further breakdowns, lack of spares and interruption of major maintenance cycles. The balance between generation versus demand as reported on 18/July/2004 by the PCO (Agency responsible for Coalition projects following the CPA, which completed its mandate as of 30/June/2004) is as follows:

  • Daily Electricity Demand: 6,400 MW
  • Daily Average Output: 4,470 MW
  • Summer peak demand 6,8007,500 MW, 35 to 40% of the summer peak demand cannot be satisfied at present. This is a highly unacceptable situation considering the summer temperatures that exist in Iraq.
  • Lack of electricity tends to affect more severely the most vulnerable groups of Iraq’s society and increases their morbidity and mortality. Ongoing efforts need to be maintained and new actions to increase electricity supply need to be initiated. In addition, significant delays have been occurring in the reconstruction work that is underway and more security related bottlenecks are expected. Baghdad, a city of 6 million (representing 1/3 of Iraq’s population) is still subjected to programmed load shedding on a rolling basis (roughly 3 hrs on 3 hrs off). This is often exacerbated by unforeseen events. For example, on 2 June and 26 July 2004, segments of Baghdad were left without power for 16 and 21 hours, respectively. These events took place in weather that is exceedingly hot. In a country with 39.7% of its population under 15 years, these events don’t go unnoticed and the need to add generating capacity to the grid is most pressing.

    Prewar Baghdad had (16-24) hours per day and was favored for distribution, the remainder of Iraq received 4–8 hours per day. Post war, Baghdad no longer has priority and therefore both Baghdad and the country as a whole received on average 15.5 hours every day as of February 2010.

    Generation

    The 1990 installed capacity of 9,295 MW consisted of 120 power-generating units in various thermal, gas turbine and hydroelectric power stations. Approximately 70% of Iraq’s installed power generating capacity was damaged or destroyed during the 1991 Gulf War. All major power stations were damaged and nearly 80% of the gas turbines units were affected. After 1991, only about 50 units were available, with a generation capacity of 2,325 MW. The construction work on three new large thermal power stations at Yousifiya, Al-Shemal and Al-Anbar were stopped, because of the ensuing sanctions.

    Thermal power stations

    The majority of the power plants in Iraq were built between the mid-1970s and 1980s, with a few small gas-fired plants commissioned in 2003. The majority of the existing power plants are thermal plants that use crude oil supported by gas-fired and hydro plants.

  • Al Dora
  • Al Taji
  • Musayab Thermal Power Station Musayab TPS (4 x 300 MW units) was commissioned in 1987 with major portions of the plant equipment supplied by Hitachi, Japan.
  • Yousfiyya power station 660 MW
  • Diwaniyya power station 250 MW
  • Rumaila power station 500 MW
  • Samawa power station 60 MW, $100-million built by Japan
  • Gas power stations

  • Al Quds power station located in Rashidiyah area, northeasten Baghdad with 10 units of capacity 800 MW when fully operational.
  • Hydro-power stations

  • Mosul Dam
  • Haditha Dam
  • Dukan Dam
  • Darbandikhan Dam
  • Imports

  • Jordan, tariff is 1 US cent per kWhr
  • Turkey, tariff 5.58 US cent per kWhr
  • Iran: As of January 2011 Iraq imports 650 MW of electricity from Iran.
  • Kuwait
  • Local diesel generators

    These are either small generators for a capacity of a house or large enough to supply a block of houses within the neighborhood supplying power for monthly fees, 14.2 US cent/kWHr.

    Iraq rebuilding projects

    As of June, 2014 Iraq spent about USD 27 billion between 2003 and 2012 to rehabilitate the power sector after decades of war and sanctions, but widespread corruption in the country has hindered development efforts and power outages continue. In 2005 the World Bank estimated that US$12 billion would be needed for near-term restoration, and the Ministry of Electricity estimated that US$35 billion would be necessary to rebuild the system fully.

  • General Electric PPHM contract of US$3 Billion. Under the agreement, GE Energy will provide multi-fuel gas turbines capable of supplying 7,000 MW of electricity.
  • Emergency Rehabilitation of Musayyib Power Station – Stage II, location Nationwide, Project cost US$33 million. Duration 24 months, Starting Date June 2005, Completion Date June 2009.
  • Al Hartha power station, Basrah, a project will double the output of the Hartha station from 400 MW to 800 MW, the total cost of the project is estimated at US$150 million which is funded by World Bank.
  • Dora power station; rehabilitation Unit 5 & 6 (steam turbine, 160 MW each) $90.8 millions JO-03-037-08 by Bechtel, personnel assistance and training for MoE $80 millions JO-04-503-03.
  • Dukan and Darbandikhan emergency Hydro Power Project with cost US$37.5 million.
  • In October 2010 it was announced that a Turkey energy company, Calik Enerji, has signed a contract, worth of US$445 million, with the Iraqi government to build a power generating station in Al Khairat, Karbala city in central Iraq.The generating capacity of the station amounts to 1,250 MW.
  • In October 2010 Enka Insaat won a US$267.5 million deal to build a power plant and install six turbines in Ninawa Governorate in northern Iraq.
  • In October 2010 MoE announced that Eastern Lights will install four turbines in an existing plant in Baghdad under a contract worth US$204.8 million.
  • Iranian company Tavanir has built Al Sadr Power Plant and is currently expanding it to 640 MW. Iran also plans to build 2000 MW of installed capacity in Iraq and increase its export to Iraq to 1250 MW by summer 2012.
  • References

    Electricity sector in Iraq Wikipedia