Rahul Sharma (Editor)

Electricity sector in Haiti

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Installed capacity (2006)
  
270 MW

Share of renewable energy
  
30% (hydro)

Average electricity use (2006)
  
75 kWh per capita

Share of fossil energy
  
70%

GHG emissions from electricity generation (2003)
  
0.2 Mt CO2

Electricity coverage (2006)
  
12.5% (total); (LAC total average in 2007: 92%)

The largely government owned electricity sector in Haiti referred to as Électricité d'Haïti (ED'H for "Haiti Electric Utility", faced a deep crisis characterized by dramatic shortages and the lowest coverage of electricity in the Western Hemisphere in 2006. with only about 12.5% of the population (25% if illegal connections are accounted for)having regular access to electricity. In addition, Haiti’s large share of thermal generation (70%) makes the country especially vulnerable to rising and unstable oil prices.

Contents

Haiti has the smallest public sector in the LAC region, which in this case is reflected by a weak institutional capacity within the Ministry of Public Works, Transport and Communications (MTPTC). Since the MTPTC is the main government body in charge of the electricity sector, this lack of capacity affects directly the performance of the sector.

Voltage and frequency

Electricity in Haiti is 110 Volts, alternating at 60 cycles per second.

Installed capacity

Most of the generation infrastructure in Haiti is very old and costly to maintain and operate. In 2006, total installed capacity was only 270 MW, of which about 70% was thermal and 30% hydroelectric. There are currently three large thermal plants and one hydroelectric plant serving the metropolitan area and some smaller thermal and hydroelectric plants in the provinces. The most important plants are:

  • Péligre, an hydroelectric plant with 54 MW of installed capacity. However, its actual power varies between 30 MW in the rainy season and 10 MW in the dry one.
  • Carrefour, a 50 MW thermal plant with just 12 MW of actually available capacity.
  • Varreux 1 and 2, two thermal plants with installed capacities of 33 MW and 21 MW respectively which can just provide 12.5 MW.
  • The large difference between installed and available capacity stems from serious maintenance deficiencies which have led, for example, to just one quarter of hydroelectric capacity to be available. The repairs carried out in Varreux and Carrefour should allow for 15 MW of additional capacity.

    Generation in 2003 was 550 GWh, with 54% coming from thermal sources and the remaining from hydroelectric ones.

    Demand

    In 2003, total electricity consumption in Haiti was 510 GWh, Average per capita consumption in 2004 was 75 kWh, the lowest in the LAC region. The share for each sector is as follows:

  • Residential: 60%
  • Industrial : 20%
  • Transport : 15%
  • Services : 5%
  • Demand vs supply

    The Haitian electricity sector has a national installed capacity that is largely insufficient to meet a demand of 157 MW in Port-au-Prince and of 550 MW at the national level. This electricity shortage has created a situation in which tens of thousands of households and institutions (e.g. hospitals, schools) have to rely on their own diesel generators and as a result spend large portions of their income on fuel to run those generators. In order to partially address this deficit, the government has signed contracts with Sogener, Haytrac and Epower which are private power suppliers, for a total of about 135 MW.

    For the medium and long term, according to recent estimates, Haiti needs about 200 MW of new generation capacity by the year 2010 and up to 750 MW by 2020.

    Access to electricity

    In Haiti, only 12.5% of the population have access to electricity “officially”, although the Ministry of Public Works estimate that the coverage could be around 25% when irregular connections are considered. In the capital, Port-au-Prince, the access rate is about 45%.

    Some towns in Haiti, such as the capital of the Nord-Est Department Fort-Liberté, have an electricity distribution network, but have been effectively abandoned by the national utility EdH for about a decade. Users thus have to rely entirely on small, privately owned generators to meet their electricity demand.

    Interruption frequency and duration

    Those who have access to electricity received on average 10 hours of electricity a day, with disparities among the areas covered. People have freezers and refrigerators to cool food, not to preserve it. These coolers consume too much electricity to run off batteries, for those who can afford them. Therefore, they are disconnected when the power is off.

    Distribution and transmission losses

    The public utility Electricité d’Haïti (EDH), a member of Caribbean Electric Utility Services Corporation (CARILEC), suffers from high inefficiencies, with more than 75% estimated technical and commercial system losses. This high percentage results from improper maintenance due to lack of financing; triggering incidents (e.g. fires); theft; obsolescence of information systems, which prevents proper identification of customers, billing and accounting and in turn impacts quality of service and losses. The ratio of energy unpaid to energy produced is among the highest in the world, with an estimated 35% of the energy produced being stolen. Many residents cannot afford the high costs of electricity, so resort to stealing.

    EDH’s financial situation is precarious. Utility bills cover less than 50% of electricity generated. In some cases, third parties install transformers to steal electricity from EDH high voltage lines and charge consumers for the stolen electricity. The combined losses require an annual subsidy from the Government of Haiti of $120 million to maintain operations.

    Policy and regulation

    The institutional framework of the electricity sector in Haiti is weak. The entity in charge of the energy sector is the Ministry of Public Works, Transports and Communications (MTPTC). The minister is also the president of the executive board of the state-owned power company, EdH (Haiti Electricity Company). The board of directors of EdH, which had not met for many years, began to meet again beginning in September 2005 (although recent meetings have not happened), aiming at better transparency for the management of the public utility.

    However, the elimination of the secretary for energy, mines and telecommunications (SEEMT) in 2005 deprived the government of the technical capacity required to address the crisis in the electricity sector.

    The Council of Modernization of Public Enterprises (CMEP), which was created as a technical entity to oversee the reform process of public enterprises, is officially in charge of following up on the medium term program to rehabilitate EDH.

    Generation, transmission and distribution

    Electricité d’Haïti (EdH) holds the monopoly for electricity generation, transmission and distribution in the country. However, as a result of the inability of EdH to meet the electricity demand, the private sector has been present for ten years in the generation subsector through private power suppliers who sell their electricity to EdH at an agreed price. After the expiration of the existing contract with Alstom, Sogener is currently the only IPP that generates and sells electricity to EdH.

    History

    Haiti has limited energy resources: no petroleum or gas resources, small hydroelectricity potential and rapidly declining supplies of wood fuels. With very limited access to electricity, most of the population in Haiti depends on charcoal as a source of energy.

    The National Electricity Company (Electricité d’Haïti – EDH) was created in 1971 to operate the newly built Péligre hydroelectric plant and the nation’s power system. Electricity consumption increased sixfold between 1970 and 1987, but just 10% of the population had access to electricity by 1986, a number that, if not accounting for illegal connections, has not varied much in the last 20 years. In the late 1980s, installed capacity was estimated at 147 MW (compared with 240 MW in 2003).

    The Organic Law from the 20th of August 1989 defined EDH’s responsibilities. EdH administers the hydroelectric plants (Péligre, Guayamouc and other smaller ones), the thermal plants (Varreux and Carrefour), other small generators and the distribution system. However, the system remains largely dysfunctional, with no power links between the capital and the provincial cities, or between provincial cities, and with unpredictable generation due to fluctuating supplies of imported petroleum and hydroelectricity shortfalls in the dry seasons. This situation leads to frequent energy rationing in which large businesses and residential users are forced to rely on expensive back-up generators. In order to try to overcome its financial problems, EDH charges high electricity tariffs (the highest in the Caribbean in the 1980s). As a result, many people established illegal connections (one in four urban residents as per estimates at the end of the 1980s), a practice that has prevailed ever since.

    2000s developments

    In March 2004, following the resignation of President Jean-Bertrand Aristide, a transition government was created. This government, together with the donor community, prepared the Interim Cooperation Framework (ICF), which set a strategy for increasing political and social stability and promoting economic growth. This framework was to guide investments of the international community until September 2007. One of the top priorities laid out was the re-establishment of continuous electricity service. The progress assessment conducted by the ICF in the end of 2005, showed that only 25% of the objectives for the electricity sector had been met.

    The electricity sector currently faces crucial problems: existence of a limited pool of experts, political interference, weakness in the institutional framework, fragmentation of the main actors and lack of strategic coordination and leadership. The lack of financial resources for maintenance, poor management practices, fraud and corruption and political interference lay at the core of these problems, which reflect into poor and unreliable provision of electricity services to end users, which in turn results in lack of willingness of affected consumers to pay for mediocre or often non-existent services.

    After the election of René Préval as President of Haiti, the Ministry of Public Works, Transport and Communications (MTPTC) released in 2006 a draft Strategy for the Development of the Electricity Sub-Sector for the period 2006-2011. According to this strategy, in the medium to long term, EDH should undertake the following actions: (i) renovate the existing generation and distribution installations, (ii) construct medium-sized plants in the North, South and Artibonite regions when the interconnections are ready, (iii) build the national transmission network to connect the networks of the North, the Artibonite, the South, the West and the South, (iv) build a 120 to 260 MW oil-fired or coal-fired plant, and (v) undertake a vast rural and urban electrification program. However, priorities are not defined yet and financing for the implementation of the strategy is still to be obtained.

    Tariffs

    The average residential tariff in 2006 was US$0.176/kWh, which is considerably higher than the weighted averages for the LAC region (US$0.115/kWh). However, this average tariff is still lower than the price charged to EdH by the private producers (US$0.210/kWh and US$0.206/kWh for Alstom (before expiration of their contract) and Sogener respectively). In August 2009, the electricity tariff was increased to 12-14 HTG/kWh resp. US$0.30 - 0.35.

    Subsidies

    The inability of EdH to cover its operating expenses, has led the Haitian State, through the Ministry of Finance, to heavily subsidize the sector with transfers for the purchase of fuel and for the purchase of electricity from two independent power producers (IPPs). These payments, which represent 1% of GDP, have created an unsustainable fiscal burden for the government.

    Investment and financing

    Investment in the electricity sector in Haiti has been very low. The combination of a culture of non-payment for electricity services, fairly high consumer tariffs, a low base of metered customers, a lack of support from the authorities to combat corruption and fraud, a weak anti-fraud unit in EdH and widespread electricity theft had led to extremely low levels of cost recovery, which in turn has resulted in an inefficient and decrepit electricity network and a high level of financial losses.

    According to studies financed by different donors, some of which need to be updated, there is an important need for investment in generation, transmission and distribution. The estimates are:

  • Generation: US$135 to US$395 million (including medium-term hydroelectricity projects)
  • Transmission and distribution: US$55 million
  • In fact, investment in the transmission network is essential since there is almost no reliable network between the main production and consumption centers and the existing lines thus would not be able to transmit newly generated electricity to the consumers.

    As part of its Strategy for the Development of the Electricity Sub-Sector, the Haitian government hopes to be able to undertake the rehabilitation and renovation of the electricity system in the capitals of the ten departments and in some other cities. The cost of this project has been estimated at US$42 million.

    Summary of private participation in the electricity sector

    Electricité d’Haïti (EdH) holds the monopoly for electricity generation, transmission and distribution in the country. However, as a result of the inability of EdH to meet the electricity demand, the private sector has been present for ten years in the generation subsector through private power suppliers who sell their electricity to EdH at an agreed price. After the expiration of the existing contract with Alstom, Sogener is currently the only IPP that generates and sells electricity to EdH. Currently, 23% of generation capacity is in private hands.

    Responsibility for the environment

    The Ministry of the Environment (MDE), created in 1994, is the institution in charge of promoting sustainable development and support the conservation of the environment.

    Greenhouse gas emissions

    OLADE (Latin American Energy Organization) estimated that CO2 emissions from electricity production in Haiti in 2003 were 206,000 tons of CO2, which corresponds to 12% of total emissions from the energy sector.

    CDM projects in electricity

    Currently (November 2007), there aren’t any CDM projects in Haiti.

    References

    Electricity sector in Haiti Wikipedia