Canyon Ferry Dam is a concrete gravity dam in a narrow valley of the Missouri River, United States, where the Big Belt Mountains and the Spokane Hills merge, approximately 68 miles (109 km) downstream from the confluence of the Gallatin, Madison, and Jefferson Rivers, and about 20 miles (32 km) east of the city of Helena, Montana. The dam is for flood control, irrigation, recreation and hydroelectric power. The building of the dam created a reservoir known as Canyon Ferry Lake.
Contents
Map of Canyon Ferry Dam, Helena, MT 59602, USA
BackgroundEdit
In 1941, the first study for the dam was carried out by the Bureau of Reclamation, the Montana Water Board and Montana Power Company. Known as the Canyon Ferry Unit, the dam and power plant were approved by the Flood Control Act of 1944 which was signed on December 22. Construction began on May 24, 1949, and was completed on June 23, 1954. On December 18, 1953, the power plant's first generator became operational and the other two went online in 1954. The 1949 structure replaced the original Canyon Ferry Dam 1.5 mi (2 km) upstream. The original dam was constructed between 1896 and 1898 by the Helena Water and Electric Power Company. It was a timber crib dam with rock-fill and was 29 ft (9 m) high and 485 ft (148 m) long.
DesignEdit
The dam is a 225 ft (69 m) tall concrete gravity type has a length of 1,000 ft (305 m). The crest of the dam is 20 ft (6 m) while the base is 173 ft (53 m). The dam structure compromises a total of 414,400 cu yd (316,832 m3) of concrete. The dam's spillway is located on its central portion and is controlled by four radial gates. It has a maximum discharge of 150,000 cu ft/s (4,248 m3/s). Adjacent to the spillway is the dam's power plant which contains three 16.5 MW Francis turbine generators for an installed capacity of 50 MW. Each turbine is fed with water by a 13.5 ft (4 m) diameter penstock. At a normal elevation of 3,797 ft (1,157 m), the reservoir contains 1,891,000 acre·ft (2.332514155×109 m3) of water.