Neha Patil (Editor)

Willow Creek Dam (Oregon)

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Opening date
  
1983

Creates
  
Willow Creek Lake

Opened
  
1983

Impound
  
Willow Creek

Impounds
  
Willow Creek

Height
  
49 m

Construction began
  
1979

Willow Creek Dam (Oregon) httpsuploadwikimediaorgwikipediacommonsthu

Location
  
Morrow County, Oregon, U.S.

Total capacity
  
gross 13,250 acre feet (16,340,000 m) usable 9,765 acre feet (12,045,000 m)

Catchment area
  
96 square miles (250 km)

Construction cost
  
37.23 million USD (as of June 18, 1997)

Operator
  
United States Army Corps of Engineers

Similar
  
Alpe Gera Dam, Shimajigawa Dam, Dworshak Dam, Gravity dam, Tarbela Dam

Willow Creek Dam is a dam in Morrow County of the U.S. state of Oregon, located just east of Heppner's city limits. It was the first major dam in the United States constructed of roller-compacted concrete.

Contents

Map of Willow Creek Dam, Heppner, OR 97836, USA

The dam's drainage basin is 96 square miles (250 km2) of arid rolling hills in the lower basin but with headwaters in the northern Umatilla National Forest. The dam's original purpose was primarily to store water for flood control, but also to serve recreation, fish and wildlife, and irrigation uses. The dam impounds Willow Creek to create Willow Creek Lake.

The lake level can be a maximum of 2,113.5 feet (644.2 m) elevation and a minimum of 2,063.0 feet (628.8 m) for a total usable storage capacity of 9,765 acre feet (12,045,000 m3).

History

A major flood killed approximately one quarter of Heppner's population in 1903—about 250 people. The flooding creek flow was 36,000 cubic feet per second (1,000 m3/s) as a result of a flash flood caused by thunderstorms, known as the Heppner Flood of 1903.

A flood control study was completed in 1962 at a total cost of $219. In 1965, a flood control project was authorized by U.S. Congress.

In 1979, the purpose of a dam project was changed to defer irrigation development for the future and eliminate water supply and water quality control.

Construction feasibility tests in 1972 placed a few layers of roller-compacted concrete. A 1:36 model (one inch equals three feet) was built and studied to determine downstream flooding and pool siltation characteristics as affected by the dam's spillway.

The dam was constructed by the Army Corps of Engineers between November 1981 and February 1983. Construction completed nearly on schedule, despite the workers initially being unfamiliar with the materials, processing, and techniques. It came in less than its budget of $50 million at $35 million. The dam's construction validated economic and construction speed benefits where 330,000 cubic meters (430,000 cu yd) of concrete were finished in less than five months at about $17 per cubic meter ($13/yd3), which includes additional efforts to correct defects.

However, as soon as the lake began filling, significant leakage was evident through the seams of the layers of concrete. The lake was drained and a $2 million remedial effort included injecting grout through bores drilled from top to bottom. The initial rate of leakage was 33 cubic meters per second (1,200 cu ft/s). After remediation, the leakage was less than 11 cubic meters per second (390 cu ft/s). Concern over the dam's safety has continued, especially with the memory of the 1903 flash flood.

Within a few years of construction, problems were noted with stratification of the water and anoxic decomposition producing hydrogen sulfide. Concerns were expressed that this could in turn give rise to sulfuric acid leading to concrete damage. Controversy continued for some years and the handling of the problem itself was criticized. In 2004, an aeration plant was installed to address the root cause, as had been called for 18 years earlier. Subsequent controversy surrounded the politics of a small town being used as an experiment for new construction technology. SolarBee devices to circulate the water were installed in 2009.

The dam won an American Society of Civil Engineers (ASCE) award in 1985.

References

Willow Creek Dam (Oregon) Wikipedia