Opening date 2018 Purpose Hydroelectricity | Status Under construction Type of dam Run-of-river Construction began 2011 | |
![]() | ||
Owner(s) Upper Tamakoshi Hydropower Limited Similar Chilime Hydropower Plant, West Seti Dam, Marshyangdi, Kaligandaki A Hydroele, Dudh Kosi |
The Upper Tamakoshi Hydroelectric Project is a 456 MW peaking run-of-the-river hydroelectric project in Nepal. It the largest hydroelectric project in Nepal, and is slated for completion in 2018. It is sited on the Tamakoshi River (also spelled Tamba Koshi), a tributary of the Sun Kosi river (also spelled Sunkoshi), near the Nepal–Tibet border.
Contents

The Upper Tamakoshi Hydroelectric Project is a Nepal national priority project. When it is completed, it is projected be the largest hydroelectric plant in Nepal, with a power output equivalent to two-thirds of Nepal's current power generation. The Project is entirely financed from domestic financial institutions and companies.

Financing and organization

Nepal Electricity Authority (NEA) has established an autonomous company named Upper Tamakoshi Hydropower Limited (UTKHPL) in March 2007 (2063/11/25 B.S.) as an executing agency for the implementation of the Project. There are six full time and two invitee members in the Board of Directors (BoD) at present. Out of six full time members, four members from NEA, one from Employees Provident Fund (EPF) and one from Nepal Telecom (NTC) are representing in the BoD. Similarly, representatives of Citizen Investment Trust (CIT) and Rastriya Beema Sansthan (RBS) are also in the BoD as invitee members.

The majority share (51%) of the Company is held by four public entities, namely, Nepal Electricity Authority (NEA), Nepal Telecom (NTC), Citizen Investment Trust (CIT) and Rastriya Beema Sansthan (RBS). NEA has 41% stake, NTC has 6% and CIT & RBS each has 2% stake in the Company. Similarly, general public and residents of Dolakha District will have 15% and 10% share respectively. The remaining 24% share will be taken over by contributors in Employees Provident Fund (EPF), NEA & Companys staffs and staffs of financial institutions providing loans.
Construction

Construction began in February 2011. Sinohydro is managing construction. The Nepalese Army was mobilized to provide security to the site in 2012, after it was reportedly threatened by vandalism and threats to construction staff and foreign workers. Work was disrupted by the April 2015 Nepal earthquake, after which over 200 Chinese workers were evacuated. Work was disrupted throughout the construction project by labor strikes. The earthquake also caused damage to roads and bridges and buried the troop barracks at the site.
Infrastructure

Infrastructure for the plant includes a 142 m long, 25 m high underground powerhouse hall near Gongar Khola, with six Pelton wheels; a 22 m high × 60 m wide dam; a 360 m high surge shaft; and a total of 16 km of headrace and tailrace tunnels. The gross head will be 822 m.