Trung Sơn Dam

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Country
  
Vietnam

Opening date
  
2016 (est.)

Height
  
84.5 m (277 ft)

Province
  
Thanh Hoa Province

Construction cost
  
410.7 million USD

Impound
  
Ma River

Status
  
Under construction

Impounds
  
Ma River

Catchment area
  
14,660 km²

Owner
  
Vietnam Electricity

Construction began
  
2012

Trung Sơn Dam wwwworldbankorgcontentdamWorldbankFeature20

Location
  
Trung Sơn commune, Quan Hóa District, Thanh Hóa Province

Similar
  
Lai Châu Dam, Đa Nhim Hydroelectric Power St, Sơn La Dam, Hòa Bình Dam, Hàm Thuận – Đa Mi hy

The Trung Sơn Dam (Dự Án Nhà máy Thủy điện Trung Sơn) is a hydroelectric power station under construction on the Ma River in northwestern Vietnam. Located in the Trung Sơn commune, Quan Hóa District, Thanh Hóa Province, it is approximately 95 kilometres (59 mi) southwest of Hòa Bình city, and 195 kilometres (121 mi) northwest of Thanh Hóa city. The dam will create a reservoir which covers a large area of the Mường Lát and Quan Hóa Districts in the Thanh Hoa province as well as part of the Mộc Châu District in Sơn La Province. It is approximately 9.5 kilometres (5.9 mi) from the Vietnam–Laos border.

Contents

Map of Trung S%C6%A1n Dam, Trung S%C6%A1n, Quan H%C3%B3a, Thanh Ho%C3%A1, Vietnam

The Project

The Trung Sơn hydropower project is owned by Trung Sơn Hydropower Company Limited (TSHPCo), the entity established by Vietnam Electricity (EVN) in Decision No. 106/QD-ENV dated March 17, 2011. TSHPCo is responsible for the management, construction and operation of the Trung Sơn hydropower project.

The project will provide both power generation and flood control. The powerhouse is designed to contain four generating units with a total capacity of 260 MW and an annual output of 1,018.61 GWh,, a significant addition to the national grid. The flood control storage of 112 million cubic metres (4.0×10^9 cu ft) will help prevent floods downstream.

The project will cost a total of VND 7,775,146 million (equivalent to US $410.68 million). This includes US $330 million from a World Bank loan, which was signed by the Socialist Republic of Vietnam and the World Bank on June 28, 2011. Additionally, the project was given slightly over US $80 million from the counterpart fund of (EVN).

The project has created social, environmental and community relation programs to mitigate anticipated and unanticipated issues with populations either directly or indirectly impacted, the Resettlement, Livelihoods and Ethnic Minorities Development Program (RLDP). These populations consist of approximately 10,600 people (2,327 households), of which 7,012 (1,516 households) will be directly impacted in the main project area, resulting in a total of 533 households having to be resettled. The RLDP includes a Resettlement Plan (RP), a Community Livelihoods Improvement Plan (CLIP) and an Ethnic Minorities Development Plan (EMDP).

In addition, management has prepared a Supplementary Environmental and Social Impact Assessment (SESIA) with Environmental Management Plan (EMP) for the project. This plan includes principles, approaches, procedures and methods to be used to control and minimize environmental impacts of all project-related construction and operation activities. Compared with fossil-fuel based energy plants of the same size, the dam produces far less greenhouse gas emissions (GHGs). TSHPCo maintains a website at www.trungsonhp.vn where public information is routinely updated.

Main parameters

  • Catchment basin area: 14,660 square kilometres (5,660 sq mi)
  • Reservoir volume: 348.5 million cubic metres (12.31×10^9 cu ft)
  • Reservoir area when at full capacity: 13.13 square kilometres (5.07 sq mi)
  • Full capacity water level: 160 metres (520 ft)
  • Minimum operating water level: 150 metres (490 ft)
  • Maximum flood control storage: 150 million cubic metres (5.3×10^9 cu ft)
  • Regular flood control storage: 112 million cubic metres (4.0×10^9 cu ft)
  • Installed electrical capacity : 260 MW
  • Annual electrical output: 1,018.61 GWh
  • Dam crest length: 513 metres (1,683 ft)
  • Dam width at the top: 8 metres (26 ft)
  • Dam height: 84.5 metres (277 ft)
  • A power plant containing four 65 MW Francis turbines (total installed capacity of 260 MW), each designed for a maximum water head of 72.02 metres (236.3 ft)
  • A 65-kilometer, 220-kV transmission line connecting to the national grid
  • A 20.4-km access road
  • Components

    The project is composed of four components:

  • Dam and Ancillary Construction: (i) Dam and ancillary works; (ii) Access road and bridges; (ii) Temporary transmission line to supply power for construction; and (iv) Project management
  • Permanent power transmission line: 220 kV double-circuit line to connect to the national grid in the Tan Lac district
  • Social and environment impact mitigation concerns: (i) Resettlement; (ii) Livelihoods and ethnic minorities development; (iii) Public health support; and (iv) Environmental management
  • Capacity development and scale-up: Support to bring hydropower projects up to international standards
  • Key milestones

  • Commencement of main civil works: November 2012
  • River diversion: Quarter 4, 2013
  • Impoundment: October 2016
  • Operation of Unit No. 1: Quarter 4, 2016
  • Operation of Unit No. 4: Quarter 2, 2017
  • References

    Trung Sơn Dam Wikipedia