Tangir Hydropower Project

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Status
  
Proposed

Impounds
  
Tangir River

Type of dam
  
run-of-the-river

Tangir Hydropower Project

Official name
  
Tangir Hydropower Plant

Location
  
Chilas, Gilgit-Baltistan, Pakistan

Owner(s)
  
Water and Power Development Authority (WAPDA)

Tangir Hydropower Plant (THPP) is a proposed (Expression of Interest for Development phase) small, low-head, run-of-the-river hydroelectric power generation station of 15 megawatt generation capacity (three units of 5 MW each), located on the left bank of Tangir River in Gilgit-Baltistan province of Pakistan about 30 km downstream of Diamer-Bhasha Dam and 430 km from Islamabad. The project area is accessible from Chilas by Karakoram Highway and a jeepable road leads to project area.

Contents

Pakistan Water and Power Development Authority (WAPDA) intends to develop 15 MW Tangir Hydropower Project under Public Private Partnership (PPP) mode. The project would be implemented under the "Policy for Power Generation Projects- 2002" and would revert to the Government of Pakistan after the concession period. The Government of Pakistan/ Government of Gilgit-Baltistan/ WAPDA would provide up to one third of the equity in the Partnership. It is located at 35°26'N 74°05'E. It is a small hydel power generating plant proposed to be constructed and put in commercial operation with the Average Annual generating capacity of 112.34 million units (GWh) of least expensive electricity.

Salient Features

Weir Elevation: 1430 m
Powerhouse Elevation: 1215 m
Catchments Area: 740 km2
Mean Annual Discharge: 24.52 m3/s
Design Discharge: 8.70 m3/s
Gross Head: 215 m
Net Head: 202.9 m
Capacity: 15.0 MW
Mean Annual Energy: 112.34 GWh
Plant Factor: 85.5 %
Headrace tunnel length: 3340 m
Penstock/pressure shaft: 350 m, 1.75 m
No. & Type of Turbine: 3 Pelton-type, 500 rpm
Total Project Cost with IDC: $30.967 Million
Cost/KWh: 4.29 US cent
EIRR: 35.0 %
FIRR: 22.56 %
B/C Ratio: 2.23

Current Status

The project has been identified by HPO and a Pre-feasibility study is in progress.