Built 1878 Opened 1878 | Area less than one acre NRHP Reference # 74001419 Added to NRHP 10 September 1974 | |
![]() | ||
Address 5221 Stonelick Williams Corner Rd, Batavia, OH 45103, USA Hours Open today ยท Open 24 hoursTuesdayOpen 24 hoursWednesdayOpen 24 hoursThursdayOpen 24 hoursFridayOpen 24 hoursSaturdayOpen 24 hoursSundayOpen 24 hoursMondayOpen 24 hoursSuggest an edit Similar Pfarr Log House, Pattison Park, Bethel Methodist Church, Promont, Grant Birthplace |
Stonelick covered bridge time lapse
The Stonelick Covered Bridge is located on Stonelick-Williams Corner Road in Clermont County, Ohio, crossing the Stonelick Creek. The one-lane covered bridge was built in 1878. It is 140 feet long and supported using a 12-panel Howe truss. The property was added to the National Register on September 10, 1974, being the last surviving covered bridge in Clermont County.
Contents
Damage, rehabilitation, and collapse
In 1983 a garbage truck broke through the floor. It also suffered some fire damage in 1991. A creek bank revetment project was undertaken in 1999 to prevent further erosion from undermining the bridge.
The bridge was permanently closed to all traffic in May 2010 after its floor and supporting structure was severely damaged by an overweight truck. Repair and rehabilitation, including improvements to raise the weight limit from 3 to 12 tons, was initially estimated to cost $1.2 million USD.
After funds and approval for the rehabilitation project were obtained, a request for bids was made in April 2013, with an updated engineer's estimate of work at $720,000. Construction work began in October 2013. A temporary steel falsework was constructed under the bridge to give additional structural support during the work and to provide work platforms, followed by the removal of all the siding. Additional work to be performed included the replacement of all siding and the roof, additional structural support, repointing and grouting of stonework, and addition of lighting and security systems.
On February 11, 2014 the upper shell of the bridge unexpectedly collapsed, falling off the deck and into the river bed, as repair work was being performed. All workers escaped without serious injury. After assessing the collapse, the County and the contractor have determined to continue the process of restoring the bridge. They now plan to completely disassemble the bridge, inspect each component to determine whether it needs to be replaced, and continue the restoration as originally planned, using as many original components as possible.