Construction began July 2010 Construction cost US$600 million Phone +971 2 894 6000 | Status Operational Commission date 17 March 2013 Site area 250 ha | |
![]() | ||
Hours Open today · Open 24 hoursFridayOpen 24 hoursSaturdayOpen 24 hoursSundayOpen 24 hoursMondayOpen 24 hoursTuesdayOpen 24 hoursWednesdayOpen 24 hoursThursdayOpen 24 hoursSuggest an edit Owners Masdar (60%), Abengoa (20%), Total S.A. (20%) Similar Al Mirfa Power Company, Mohamed Abdulrah Al‑Bahar, Tilal Liwa Hotel, Al Noor Hospital, Madinat Zayed Police St |
Shams Solar Power Station (شمس /šhams/ meaning "Sun" in Arabic) is a concentrating solar power station near Madinat Zayed, Abu Dhabi, the United Arab Emirates. The solar power station is located approximately 120 kilometres (75 mi) southwest of Abu Dhabi and 6 kilometres (4 mi) from Madinat Zayed on the road from Tarif to the Liwa Oasis. It became operational on 17 March 2013.
Contents
The first part, Shams 1, uses parabolic trough technology and has a capacity of 100 megawatts (MW), which makes it among the largest parabolic trough power stations in the world. Shams 1 has been commissioned in early 2013 and will be followed by Shams 2 and Shams 3 stations.
Description
Shams 1 is a 100 MW concentrating solar power station which uses parabolic trough technology. It displaces 175,000 tons of CO2 per year and its power output is enough to power 20,000 homes. The station consists of 258,048 parabolic trough mirrors, 192 solar collector assembly loops with 8 solar collector assemblies per loop, 768 solar collector assembly units, and 27,648 absorber pipes. It covers an area of approximately 2.5 square kilometres (0.97 sq mi).
The basic and detailed engineering have been developed by AG Ingeniería. The project is consulted by Fichtner Consulting Engineers. The equipment is designed and delivered by Foster Wheeler. The power station is equipped by Abengoa Solar's ASTRO collectors. The 125 MW steam turbine is provided by MAN Turbo, parabolic glass mirrors are provided by Flabeg, PTR 70 absorber tubes are provided by Schott AG, and Therminol heat transfer fluid is provided by Solutia.
In October 2010 it was reported that because of "substantial" atmospheric dust, solar radiation received by Shams' solar collectors was less than expected and more collectors would be required.
Technical specifications
Developer
The project is developed by the Shams Power Company, a special purpose vehicle of Abu Dhabi Future Energy Company (Masdar) in cooperation with Spain's Abengoa Solar and France's Total S.A. Masdar has 60% in the project while Abengoa Solar and Total S.A. each have 20%. The power station is developed under a 25-year build, own and operate contract. Bids to build and operate the power station were made by several international consortia. In addition to Abengoa Solar and Total S.A., Saudi Arabia's ACWA Power and Spain's Iberdrola, Germany's MAN Ferrostaal and Solar Millennium, and Spain's Grupo Cobra and Grupo Sener made their bids.
Financing
The construction cost of Shams 1 is about US$600 million. The project is financed by 10 regional and international lenders including BNP Paribas, the National Bank of Abu Dhabi and Société Générale.