There have been no operational railways in Libya since 1965, but various lines existed in the past. An extensive system is now being developed and under construction.

Contents

History


The Kingdom of Italy built in Libya nearly 400 km of railways with 950 mm gauge. The last line the Italians started to create was the Tripoli-Benghazi in summer 1941, but their defeat in World War II stopped it at the beginning.

A 950 mm (3 ft 1 38 in) gauge network centred on Tripoli was opened from 17 March 1912 as part of the Italian occupation campaign. This extended from Tripoli 120 km west to Zuwara, 100 km south to Gharyan and 10 km east to Tajura.

A 750 mm (2 ft 5 12 in) (later 950 mm) gauge railway was built east from Benghazi; the main route was 110 km long to Marj and was opened in stages between 1911 and 1927. Benghazi also had a 56 km branch to Suluq opened in 1926.

Military extensions of some 40 km were made from Marj towards Derna in World War II. This was the final line to close, at the end of 1965.

The standard gauge Western Desert Extension was built from a junction 10 km east of Matruh Egypt to Tobruk during WW2 to assist in the Allied defence of the area. In 1942 this 350 km route was completed as part of Allied advance across North Africa. The 125 km Libyan section west of Sollum was removed after closure from 20 December 1946, though the Egyptian Railways Sollum branch still sees occasional freight.

Plans

Beginning in 1998, the Libyan government has been planning for an 3170 km 1,435 mm (4 ft 8 12 in) (standard gauge) network. A line parallel to the coast will eventually form part of a North African link between Tunisia and Egypt. The section from the border with Tunisia at Ras Ajdir, then via Tripoli to Sirte was under construction and was planned to open in 2009. China Railway Construction Corporation has contracts to start work in June 2008 on a 352 km route between Sirte and Khoms, to be finished by 2013. The east-west line will be double track.

A second line will run 800 km from iron ore deposits at Wadi Shati near Sabha to the steel works and port at Misrata from 2012.

A third line will run 554 km from Sirte to Benghazi in the East. In October 2007, RZD submitted a feasibility study for the project, and in 2008 signed a contract to begin construction, which was planned to take 4 years to complete. Work began on 30 August 2008. In August 2010, RZD awarded Ansaldo STS and SELEX Communications a contract to install signalling, telecoms, power, security and ticketing systems which is expected to take three years. Ansaldo STS and SELEX Communications are also working on signalling on new lines between Sirte and the Tunisian border, and the route to Sabha.

A trans-Saharan line is also planned, running south to Niger.

Construction has ceased during the Libyan Civil War.

As of March 2012, the plans have been delayed until further notice

In February 2013, the pre-revolution railway project has been approved for resumption by the government.

Rolling stock

On 10 June 2007 a contract was signed with American General Electric Co. for supply of locomotives and training of Libyan nationals in operational and maintenance work. The contract includes the import of spare parts and technical assistance. The first shipment will arrive Libya by mid-2009. Libya has bought one IC4 diesel multiple unit from AnsaldoBreda for evaluation. It is parked at 32°49′43″N 13°6′41″E until a network is operable.

1998

  • Libya signed contracts with Bahne of Egypt and Jez Sistemas Ferroviarios for the supply of crossings and pointwork.
  • 2008

  • November - GE to supply 15 diesel locomotives.
  • 30 August - Russian Railways begins work on 554 km Sirte to Benghazi railway.
  • 25 April - Russia to build coastal line from Sirte eastwards to Benghazi, approximately 500 km. This extends another project to build a 352 km line running from Sirte westwards via Misrata to Khoms.
  • China Railway Construction wins $2.6b bids in Libya. A west-to-east coastal railway 352 km from Khoms to Sirte and a south-to-west railway 800 km long for iron ore transport from the southern city Sabha to Misrata.
  • 2009

  • January - China Railway Construction signs contract to build 172 km from Tripoli to Ras Ajdir
  • 2010

  • March - First 14 km of 554 km long Russian Railways Sirte - Benghazi track in place. The total track laying is expected to take four years.
  • 2011

  • March - China Railway Group suspended work on the 3 projects valued in total at $4.24 billion with $3.55 billion of the project yet to be finished due to the rising violence levels in the Libyan Civil War.
  • 2013

  • February - Talks started between RZD and Libyan authorities to resume construction
  • References

    Rail transport in Libya Wikipedia