Puneet Varma (Editor)

RTS Flexible Systems Ltd v Molkerei Alois Müller GmbH and Co KG

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Court
  
Supreme Court

Citation(s)
  
[2010] UKSC 14, [2010] 1 WLR 753

Similar
  
Gibson v Manchester City Coun, Butler Machine Tool Co L, Brogden v Metropolitan Rly Co, Re Selectmove Ltd, Entores Ltd v Miles Far East Corp

RTS Flexible Systems Limited v Molkerei Alois Müller GmbH [2010] UKSC 14 is an English contract law case, concerning how it will be judged whether an agreement is reached.

Contents

Facts

Molkerei was buying automated packaging machinery, to come from and be installed by RTS. They made a letter of intent, providing for the whole contract price, contemplating full contract terms would be based on MF/1 terms. On 5 July 2005 a draft final contract was produced, but saying it would not be effective until executed and exchanged. Work began anyway. On 25 August terms were varied. There was a dispute about which terms the contract was on.

The Judge held that after the letter of intent expired, they entered a contract for RTS to do the work for an agreed price, but that did not include the final draft version of the MF/1 terms. The Court of Appeal held no contract arose after the letter of intent expiry at all. Molkerei argued there was a contract of expiry, not on the MF/1 terms, and RTS argued there was no contract, or if there was it was on MF/1 terms, as amended through the negotiations.

Judgment

Lord Clarke held that it was too dogmatic to say the "subject to contract" terms would be the ones that were binding, because it always depends on the circumstances. They had reached a binding agreement on or about August 25 on the terms agreed on or before July 5 as subsequently varied, and that that agreement was not subject to contract. This case illustrated the perils of beginning work without a precise basis for payment.

References

RTS Flexible Systems Ltd v Molkerei Alois Müller GmbH & Co KG Wikipedia