Puneet Varma (Editor)

Nurek Dam

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Purpose
  
Power

Opening date
  
1972-1980

Length
  
700 m (2,300 ft)

Opened
  
1980

Owner
  
Barqi Tojik

Architect
  
Armen Chaltykjan

Status
  
Operational

Impounds
  
Vakhsh River

Height
  
304 m

Area
  
98 km²

Construction began
  
1961

Nurek Dam httpsuploadwikimediaorgwikipediacommons66

Location
  
Nurek, Border of Khatlon district and Districts of Republican Subordination, Tajikistan

Similar
  
Enguri Dam, Grande Dixence Dam, Xiaowan Dam, Sangtuda 1 Hydroelectric Power Pl, Sarez Lake

Nurek dam in tajikistan


The Nurek Dam (Tajik: Нерӯгоҳи обии Норак, Nerūgohi obii Norak, Tajiki for Nurek Hydro-electric Station) is an earth-fill embankment dam on the Vakhsh River in Tajikistan. Its primary purpose is hydroelectric power generation and its power station has an installed capacity of 3,015 MW. Construction of the dam began in 1961 and the power station's first generator was commissioned in 1972. The last generator was commissioned in 1979 and the entire project was completed in 1980 when Tajikistan was still a republic within the Soviet Union. At 300 m (984 ft), it is currently the second tallest man-made dam in the world. The Rogun Dam, also along the Vakhsh in Tajikistan, may exceed it in size when completed.

Contents

Map of Nurek Dam, Nurek, Tajikistan

Construction

The Nurek Dam was constructed by the Soviet Union between the years 1961 and 1980. It is uniquely constructed, with a central core of cement forming an impermeable barrier within a 300 m (980 ft)-high rock and earth fill construction. The volume of the mound is 54 million m3. The dam includes nine hydroelectric generating units, the first commissioned in 1972 and the last in 1979. An estimated 5,000 people were resettled from the dam's flooding area.

The dam is located in a deep gorge along the Vakhsh River in western Tajikistan, about 75 km (47 mi) east of the nation's capital of Dushanbe. A town near the dam, also called Nurek, houses engineers and other workers employed at the dam's power plant.

Electricity generation

A total of nine Francis turbine-generators are installed in the Nurek Dam's power station. Originally having a generating capacity of 300 MW each (2,700 MW total), they were redesigned and retrofitted between 1984 and 1988 so now have a capacity of 335 MW each (3,015 MW total). As of 1994, this formed most of the nation's 4.0 gigawatt hydroelectric generating capacity, which was adequate to meet 98% of the nation's electricity needs.

Reservoir

The reservoir formed by the Nurek Dam, known simply as Nurek, is the largest reservoir in Tajikistan with a capacity of 10.5 km3. The reservoir is over 70 km (40 mi) in length, and has a surface area of 98 km2 (38 sq mi). The reservoir fuels the hydroelectric plant located within the dam, and stored water is also used for irrigation of local agricultural land. Irrigation water is transported 14 kilometers through the Dangara irrigation tunnel and is used to irrigate about 700 km2 (300 sq mi) of farmland. It is suspected that the reservoir may have caused induced seismicity when being impounded.

References

Nurek Dam Wikipedia