Mtwara–Dar es Salaam Natural Gas Pipeline

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
General direction
  
South to North

Passes through
  
Somanga, Tanzania

Length
  
331 mi (533 km)

From
  
Mtwara, Tanzania

Type
  
Natural gas pipeline

Commissioned
  
10 October 2015

The Mtwara–Dar es Salaam Natural Gas Pipeline (MDNGP), is a pipeline that transports natural gas from Tanzania's natural gas fields in Mnazi Bay, Mtwara Region to Dar es Salaam.

Contents

Location

The pipeline starts in Madimba Village, in Mtwara Region, in southeastern Tanzania and runs in a northerly direction, through Somanga, in Lindi Region, to end at Dar es Salaam, Tanzania's largest city, a total distance of approximately 542 kilometres (337 mi).

Background

As of October 2015, Tanzania's total electricity generation capacity stood at 1,500 MW. In 2014, hydro-power generation represented 33 percent of total capacity. Due to prolonged drought, hydro turned out to be an unreliable power source for the country. In order to diversify the national energy pool, and to take advantage of the vast natural gas resources onshore and offshore in the Mtwara and Lindi regions, a natural gas pipeline was designed and constructed, to deliver the natural gas to Dar es Salaam for use in power generation, industrial applications, household cooking and in propulsion of transport vehicles.

Technical details

The main pipeline from Madimba in Mtwara Region, to Dar es Salaam, measures 36 inches (91 cm) in diameter. At Somanga, in Lindi Region the main pipeline is joined by a smaller 24 inches (61 cm) pipeline delivering natural gas from Songo Songo Island. Both processing plants, one in Madimba and the other in Songo Songo are two trains (processing units) each and together are capable of processing 350,000,000 cubic feet (9,910,896 m3) of natural gas every 24 hours.

Construction, funding and time table

The construction contract was awarded to China Petroleum and Technology Development Company, a subsidiary of China National Petroleum Company, at a cost of US$1.225 million loan from Exim Bank of China. The Tanzania Petroleum Development Corporation invested US$274.492 million into the project. Construction began in June 2013, with commissioning in October 2015. The contract included the construction of the two-train gas processing plant in Madimba Village, Mtwara Region.