Kalpana Kalpana (Editor)

Megaprojects and Risk

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
7.6
/
10
1
Votes
Alchetron
7.6
1 Ratings
100
90
80
71
60
50
40
30
20
10
Rate This

Rate This

Country
  
United States

Publication date
  
2003

Originally published
  
2003

OCLC
  
50271600

3.8/5
Goodreads

Language
  
English

Media type
  
Print, e-book

Genre
  
Non-fiction

Megaprojects and Risk t3gstaticcomimagesqtbnANd9GcQJ71sktWWAibfrbq

Subject
  
Economics, infrastructure

Publisher
  
Cambridge University Press

Authors
  
Bent Flyvbjerg, Werner Rothengatter

Similar
  
Bent Flyvbjerg books, Project management books

Megaprojects and Risk: An Anatomy of Ambition is a 2003 book by Bent Flyvbjerg, Nils Bruzelius, and Werner Rothengatter, published by Cambridge University Press. According to chief economist and director of transportation policy at Infrastructure Management Group, Inc., Porter K. Wheeler, "this book makes an important contribution to understanding the infrastructure development process worldwide, with focus on megaprojects."

Overview

"Megaprojects" is the term applied to multibillion-dollar infrastructure developments such as massive dams and bridges, and to elaborate railways and highways. The "megaprojects paradox" is that more of these projects are being implemented, but such projects typically perform very poorly, often with substantial cost overruns and market shortfalls.

Chapters two to four examine the Channel Tunnel, which opened in 1994 at a cost of 4.7 billion pounds following cost-overruns of 80% which caused several companies to nearly go bankrupt. Denver International Airport which cost $5 billion, opened in 1995 following a 200 per cent cost overrun, and passenger traffic in 1995 was only half that expected. There were also problems with Hong Kong's Chek Lap Kok Airport, opened in 1998, which had low revenues and affected Hong Kong's economy in a negative way.

According to authors, the reason for these poor performances is that many of the participants in the process have incentives to underestimate costs, overestimate revenues, undervalue environmental impact, and overvalue economic development effects. The central problems are lack of accountability and inappropriate risk sharing which can be improved by reforming the institutional arrangements of decision making and to institute accountability at the project development and evaluation stages.