Opening date  June 1964
Installed capacity  81 Mva
Length  425 m
Construction began  March 1956
Impounds  Ohio River
Opened  June 1964
Operator  Duke Energy
Impound  Ohio River
Markland Locks and Dam httpsuploadwikimediaorgwikipediacommons99
Location  Gallatin County, Kentucky / York Township, Switzerland County, Indiana United States
Similar  Ohio River, Captain Anthony Meldahl L, Belterra Casino Resort, McAlpine Locks and Dam, Cannelton Locks and Dam

The Markland Locks and Dam is a concrete dam bridge and locks that span the Ohio River. It is 1395 feet (425.2 m) long, and connects Gallatin County, Kentucky, and Switzerland County, Indiana.

Map of Markland Locks and Dam, Kentucky 41095, USA

The locks and dam were reviewed by the Board of Engineers for River and Harbours to replace the Ohio River locks and dams Number 35, 36, 37, 38 and 39. Then the project was approved by the Secretary of the Army on March 11, 1953. Construction on the locks began in March 1956 and they were placed in operation in May 1959. The dam construction began in April 1959 and was finished in June 1964.

Federal Power Commission granted a license for Cinergy to operate a hydroelectric power plant at the dam. Cinergy was later bought by Duke Energy. The plant has a capacity of 81,000 kVA.

On September 27, 2009, the 1,200-foot lock failed and the gates "mismitered" due to a solenoid malfunction. The lock was repaired and reopened on March 1, 2010. The 1,200-foot lock chamber remained closed for 155 days, but the 600-foot lock continued to lock traffic albeit with delays.