Mông Dương is a ward of Cẩm Phả city, in Quảng Ninh Province, Vietnam. It is the site of the Mông Dương thermal power plant projects designed to reduce Vietnam's dependence on hydropower.

Contents

Map of M%C3%B4ng D%C6%B0%C6%A1ng, Tp. C%E1%BA%A9m Ph%E1%BA%A3, Qu%E1%BA%A3ng Ninh Province, Vietnam

Mông Dương power project

State-owned Electricity of Việt Nam (EVN) plans 2,200 MW of coal-fired power stations at Mông Dương.

  • Mông Dương I Thermal Power Plant (1,000 MW) was ADB part financed. The financing framework was signed in 2007. The plant required a total investment of USD $1.1 billion. NTP 15-Dec-2011, #1 COD 15-Apr-2015, #2 COD 15-Oct-2015.
  • Final Completion Ceremony at Site was on 16-Jan-2016. - Boiler Type : CFB (Foster Wheeler China) - Capacity : 250MW * 4 units

  • Mông Dương II will sell electricity to Vietnam Electricity (EVN) under a 25-year power purchase agreement (PPA) denominated in US dollars and allowing for a fuel cost pass through, protecting foreign investors from fluctuations in coal prices. NTP was on 7-Aug-2011, #1 COD was on (Plan/Actual) 04-Dec-2014/09-Mar-2015, #2 COD was on (Plan/Actual) 02-Jun-2015/24-Apr-2015. Final Completion Ceremony was on Hanoi Marriot Hotel, 26-Oct-2015.
  • - Boiler Type  : Downshot - Capacity : 560MW * 2 units