Harman Patil (Editor)

Lynx Red Line

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Type
  
Commuter rail

Services
  
Red Line

Stations
  
10

System
  
LYNX Rapid Transit Services

Locale
  
Charlotte,NC , Huntersville,NC , Cornelius,NC ,Davidson,NC and Mooresville , Mecklenburg county Iredell county

Termini
  
Uptown/Gateway Station (south) Mount Mourne (north)

The Red Line is a planned commuter rail extension for the LYNX network in Charlotte, North Carolina. The Red Line, or North Corridor, would serve as a commuter rail line between Mount Mourne in southern Iredell County and the proposed Gateway Station in Uptown Charlotte. It would primarily serve the towns of Huntersville, Cornelius and Davidson in northern Mecklenburg County.

Contents

It is proposed to follow a northerly path along the existing Norfolk Southern O Line right-of-way, roughly paralleling North Graham Street and North Carolina Highway 115, as it extends through north Mecklenburg County. It is estimated to be 25 miles (40 km) in length. Originally, it was thought to cost $261 million to complete the first phase by 2012 and an additional $112 million to complete phase two by 2019; the line would contain 1,200 parking spaces and 10 stations along the corridor. However, several issues have arisen that have increased the project's price tag, and it currently has no scheduled construction or operations start date.

Design and planning

By 2011, the Lynx Red Line was planned to be built in one phase. Due to less revenue in the transit tax, in January the Metropolitan Transit Commission voted that the Lynx Red Line along with the Blue Line extension were the top two priorities, leaving the streetcar to be funded by the city and postponing further work on the LYNX Silver Line and the Airport corridor until after the Red Line and Blue line projects were completed. The Red Line was projected to be in operation by mid to late 2018.

Lack of feasibility

By June 2011 the project had been 90% designed and an operating agreement was signed with Norfolk Southern Railway, but the project lacked nearly 80% of the needed funds to begin construction. In October 2012, The Charlotte Observer noted that "the Red Line...has little chance of federal funding, and CATS may not have enough money to pay for even a portion of construction costs. The N.C. DOT is working on creative ways to finance the project, but it appears to be years away."

On October 17, 2012, the N.C. DOT, the Red Line Task Force and CATS requested Norfolk Southern to conduct a study of the "Red Line" concept. As the Red Line would utilize the NS O-Line between Charlotte and Mooresville, the study would determine if and how both freight and passenger services could use the same line while allowing normal freight services to continue. It was estimated at a meeting of the task force on October 24 that the study would be initiated by late January 2013 and completed by early 2014, after which further feasibility studies and projections could be made. However, in early 2013, Norfolk Southern expressed its doubts that the $416 million project would be feasible.

On June 25, 2014, following the completion and release of the feasibility study, CATS officials said that the Red Line would be too costly and complicated to build. Several reasons were provided, including:

  • The continued refusal of Norfolk Southern to share its existing trackage with CATS, necessitating the construction of a new railway line parallel to the NS rails. This would increase the overall project cost by $215 million and cause "multiple disruptions to adjacent communities", as building a parallel rail line would involve construction costs, right-of-way purchases, and the complete rebuilding of all road intersections along the proposed line.
  • The project's ineligibility for federal funding due to low ridership projections.
  • The inability of CATS to fund the Red Line on its own.
  • Despite the negative assessments of the feasibility study, the Metropolitan Transit Commission, including the Red Line task force, did not take any official steps to disband the project. While the director of the N.C. DOT rail division, Paul Worley, said that he would work with Norfolk Southern officials to begin a study concerning the proposed Gateway Station, he said that the Red Line concept would not be included, as "no viable plan" for it now existed. Though the mayor of Davidson, John Woods, said the results of the feasibility study were "a serious setback," he added that developing transit in the northern portion of Mecklenburg County remained important for the region, and one possible alternative to a commuter rail line could be bus rapid transit.

    References

    Lynx Red Line Wikipedia