Puneet Varma (Editor)

Kriegers Flak (wind farm)

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Country
  
Denmark

Type
  
Offshore

Distance from shore
  
15 km

Status
  
Proposed

Max. water depth
  
25 m

Site area
  
179 km²

Kriegers Flak (wind farm) denmarkdkmediaDenmarkImagesGreen20livingS

Location
  
Baltic Sea east of Møn, south of Skåne, north of Rügen

Kriegers Flak is a proposed 600 MW offshore wind farm to be located in the Baltic Sea on the Danish part of the reef of the same name. It will form part of a new 400 MW interconnector between Denmark and Germany.

Contents

Kriegers Flak (wind farm) Seven companies prequalified for Kriegers Flak Offshore Wind Industry

Location

In 2010 the Danish Energy Agency pointed to the site as one of the most attractive for a Danish offshore wind farm. In addition to favorable wind conditions and a depth ranging from 16 m to 25 m, Kriegers Flak will also be located next to the German offshore wind farm Baltic II. Kriegers Flak will take advantage of this and be connected both to the Danish grid as well as to the 288 MW Baltic II which via the 48 MW Baltic I is connected to the German grid. The wind farm will consist of two partitions, a western of 200 MW covering 69 km2 (27 sq mi) and an eastern of 400 MW covering 110 km2 (42 sq mi); a sand dredging area separates the two areas.

Combined Grid Solution

Kriegers Flak (wind farm) VATTENFALL IN THE RACE FOR KRIEGERS FLAK NEWS FROM VATTENFALL

The Kriegers Flak combined grid solution, a serial connection of offshore wind farms into the power grids of two different countries will be the first of its kind. This has the advantage that up to the capacity of the connection the produced power can be transmitted to the country with the highest demand and price, improving the economy of the wind farms. Secondly, the connection between Denmark and Germany can act as an interconnector, so power can be transmitted from one country to the other, also in absence of power production from the wind farms themselves. This improves the overall reliability of the power grids in both countries and can also reduce the overall price of the electricity.

Kriegers Flak (wind farm) 600 MW Kriegers Flak Project Up for Grabs Offshore Wind

The combined solution was scheduled to be direct current, but the offshore converter turned out to be prohibitively expensive, and alternating current (AC) was chosen instead. Like the 150 kV cables connecting the Baltic II, Baltic I and Germany, the cables connecting Krigers Flak to Baltic II and to Denmark will be relatively short and thus using AC which is more economical. However, Germany is part of the synchronous grid of Continental Europe, while Kriegers Flak will connect to eastern Denmark, which is synchronized with the Nordic grid. As such, the non-synchronous connection requires a paired, back-to-back HVDC converter substation, to be located in Bentwisch, Germany, which already hosts the converter substation for the Kontek interconnector. The transmission capacity will be 400 MW, with the converter substation being delivered by ABB for around 140M US$. Thus, when Kriegers Flak operates at its full 600 MW capacity at least one third of the produced power must be transmitted to Denmark.

Kriegers Flak (wind farm) Kriegers Flak Offshore Wind Farm Power Technology

The 220 kV cables to Kriegers Flak will be constructed and operated by Energinet.dk, with a planned spending of 3.5 billion DKK and planned commissioning by the end of 2018. The cable will reach Denmark at Rødvig on Zealand.

Tender

Kriegers Flak (wind farm) Seven Up for Kriegers Flak Offshore Wind

The result of a call for tenders for the construction of the wind farm was expected to be published by the end of 2016. By November 2015 seven companies and consortia had been prequalified to bid on the project; an unusually high number of bidders.

The tender was won by Vattenfall in November 2016 at a price €49.90/MWh ($55.34) fixed-price with no adjustment for inflation, for 30 TWh (corresponding to 50,000 full-load hours for 600 MW, or about 11 years), without the cost of the unusual transmission project. As of 2016, it is the lowest price for offshore wind. Vattenfall has not decided on the make and model of turbines. The price is 58% lower than the cap price of €0.12 (90 øre) per kWh set in 2012. Build cost is estimated at €1.1bn-€1.3bn ($1.19bn-$1.4bn).

The low price was achieved by optimizing several aspects of the process, including the long-standing policy of authorities to prepare shovel-ready projects with all necessary permissions. This method was also used in the previous low price record at Borssele where the price is €72.70/MWh (€87/MWh with transmission). The method contrasts with the British way of tender, where applicants must perform preparatory work.

Construction

The wind farm is expected to be operational by the end of 2021.

References

Kriegers Flak (wind farm) Wikipedia