Ironbridge power stations

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Status
  
Ceased operations

Construction began
  
1929

Phone
  
+44 1952 433451

Ironbridge power stations

Country
  
England, United Kingdom

Location
  
Shropshire, West Midlands

Commission date
  
A station: 1932 B station: 1969

Decommission date
  
A station: 1981 B station: commenced 2015

Operator(s)
  
West Midlands Joint Electricity Authority (1932–1948) British Electricity Authority (1948–1954) Central Electricity Authority (1954–1957) Central Electricity Generating Board (1957–1990) Powergen (1990–2001) E.ON UK (2001–present)

Address
  
Buildwas Road, Ironbridge TF8 7BL, United Kingdom

Hours
  
Open today · 8AM–8PMWednesday8AM–8PMThursday8AM–8PMFriday8AM–8PMSaturday8AM–6PMSundayClosedMonday8AM–8PMTuesday8AM–8PM

Similar
  
Iron Bridge, Ironbridge Gorge, Meadow Inn, Best Western Valley Ho, The Library House

The Ironbridge power stations (also known as the Buildwas power stations) refers to a series of two power stations which have occupied a site on the banks of the River Severn at Buildwas in Shropshire, England. The Ironbridge B Power Station was operated by E.ON UK. The station stands near the Ironbridge Gorge World Heritage Site, where the Industrial Revolution began. Originally powered by coal, they were converted to use 100% biomass fuel. Ironbridge B Power Station stopped generating electricity on 20 November 2015, with the decommissioning process expected to continue into 2017.

Contents

Site selection

Ironbridge was selected to be the site of a large, modern "super station" by the West Midlands Joint Electricity Authority, in February 1927. The land had been identified earlier by Walsall Borough as being suitable for power generation, in 1924. The close proximity of the River Severn and several railway lines provided excellent access to both cooling water and a source for the delivery of coal. The flat land of the site, formed by fluvial processes at the end of the last ice-age, was ideal for the construction of a large turbine hall.

Ironbridge A

Construction of the first Ironbridge Power Station (later to become known as Ironbridge A Power Station) began in 1929, and the first phase was completed in 1932. The station officially opened on 13 October 1932. The full generating capacity of Ironbridge A was not realised until major expansions and the commissioning of extra boilers and generating sets had been completed in 1939. This gave the A Station a total generating output of 200 megawatts (MW).

As a result of the increasing demand for electricity after World War II, it was decided by the Central Electricity Generating Board that a new, larger, 1000 MW power station called Ironbridge B, was to be constructed alongside the A Station. The A station was partially closed on 27 October 1980, with the decommissioning of 100 MW of the station's generating capacity. The remainder of the station's capacity ceased generating electricity in 1981 and significant portions of the station were demolished in 1983 prior to being granted listed building status.

Ironbridge B

Parliamentary approval for Ironbridge B Power Station was sought and granted in 1962. Construction began in 1963, with the aim to begin generating electricity in the station in 1967. Due to construction delays, some limited industrial action and the implementation of improvements that had been pioneered during the construction of similar stations using the new 500 MW generating units, Ironbridge B didn't begin feeding power into the National Grid until the 11 June 1969. Full capacity was not reached until the second 500 MW unit began generating in February 1970. Ironbridge B Power Station stopped generating electricity on 20 November 2015 when it reached its 20,000 hours limit of generation under an EU directive, the decommissioning process is expected to continue into 2017.

Design

Project architect Alan Clark worked closely with landscape architect Kenneth Booth, to ensure that the station merged as seamlessly as possible into its natural surroundings. In this respect, the power station is unique amongst British coal-fired stations. When viewed from Ironbridge, the surroundings of the station are hidden by wooded hills. The cooling towers were deliberately constructed using concrete to which a red pigment had been added, to blend with the colour of the local soil. This had cost £11,000 in the 1960s. The towers cannot be seen at all from the world-famous landmark, The Iron Bridge. The station's single 205 m (673 ft) high chimney is fifth tallest chimney in the UK. It is the tallest structure in Shropshire, as well as being taller than Blackpool Tower and London's BT Tower.

The station's turbine hall is decoratively clad in chipped granite faced concrete panels, aluminium sheeting, and glazing. The turbine hall obscures the rather more functional metal clad boiler house from view. A free-standing administration block continues the theme of concrete panelling, albeit with extensive use of large floor to ceiling windows. Period fittings within the administration block include a board room, containing murals that reference the industries of the Ironbridge Gorge, and a grand entrance hall with a metallic mural.

So impressive were the measures taken to ensure that the power station was an asset to the gorge and not an eyesore, that it was short listed for a Royal Institution of Chartered Surveyors/The Times conservation award in 1973.

Specification

When fully operational and using 100% coal as a fuel source the power station generated electricity using two 500 MW generating sets. The turbines' blades are 1 m (3 ft 3 in) long each and when the turbines spun at their usual fixed speed of 3,000 rpm, the outermost tip of the last row of blades travel at approximately 2,000 km/h. The station uses low NOx burners and electrostatic precipitators to reduce its environmental impact. The majority of the station's ash waste was sold to the construction industry.

Coal supplies and rail access

Until June 2010, approximately 3000 – 6000 tonnes of coal was delivered to the power station every day, via a branch line railway through Madeley, Ironbridge and Coalbrookdale, crossing the River Severn via, the Grade 2 Listed Albert Edward Bridge. The railway branch joins the Wolverhampton to Shrewsbury line at Madeley Junction.

Coal was delivered variously by DBS, Freightliner and Fastline. After the trains were emptied, they were usually stabled at Warrington Arpley Yard. From 2014 until closure, an additional three trains per day travelled from Liverpool dock with biomass chips, which were by the main source of feedstock for the power station by then.

Scheduled passenger services on the branch line were stopped in the 1960s, and so the line was kept open primarily for the transportation of coal to the power station. A steam locomotive-hauled special passenger train, organised by railtour company 'Vintage Trains', visited the branch line on 3 November 2007. The tour was entitled Pannier to Ironbridge, and was hauled by former Great Western Railway 0-6-0 Pannier tank No. 9466, which ran a return trip between Tyseley, near Birmingham, and Ironbridge.

Powergen/E.oN: 1990-2015

In 1990 the CEGB was split into different companies for privatisation, and Ironbridge Power Station went through a number of ownership transfers before eventually being owned by Powergen. In 2001 Powergen was taken over by E.ON, an energy company based in Germany.

The station was the last major generator of electricity in Shropshire. The plant consumed about 1.2 million tonnes of coal and 20,000 tonnes of oil each year, and generated 2,990 GWh of electricity in 2004.

Environmental group Friends of the Earth claim that as of 2006, the station was the second worst polluting power station in the United Kingdom per megawatt output. Ironbridge had been opted out of the Large Combustion Plant Directive, which meant the station would only be allowed to operate for up to 20,000 hours after 1 January 2008, and that it must close by 31 December 2015. In 2012 Ironbridge underwent modification to allow both generating units to run on 100% biomass (wooden pellets). This reduced the generating capacity from 500MW per unit to approximately 370MW per unit.

In February 2014 fire damaged Unit 1 turbine and generator in Ironbridge B, and in May E.ON announced that the 370 MW unit would not be repaired, reducing the plant's generation capacity. Parts of the turbine casing have been removed and lie outside on-site.

Decommissioning

Following the switch off of Ironbridge B Power Station on 20 November 2015, work began on decommissioning the power station, and is expected to last into 2017.

The Telford Steam Railway has aspirations to take over the now unused railway track between the power station and Lightmoor Junction, as part of their southern extension from Horsehay through Doseley.

References