Status Operational Primary fuel Oil | Operator(s) Taipower Phone +886 2 2424 8111 Owner Taiwan Power Company | |
![]() | ||
Commission date January 1977 (Unit 1)December 1977 (Unit 2)March 1980 (Unit 3)1985 (Unit 4) Hours Open today · Open 24 hoursThursdayOpen 24 hoursFridayOpen 24 hoursSaturdayOpen 24 hoursSundayOpen 24 hoursMondayOpen 24 hoursTuesdayOpen 24 hoursWednesdayOpen 24 hours Similar 大武崙漁港停車場, 外木山漁港, 仙洞巖最勝寺, 卞家牛肉麵, 基隆小羅牛肉麵 |
The Hsieh-ho Power Plant (Chinese: 協和發電廠; pinyin: Xiéhé Fādiànchǎng) is an oil-fired power plant in Zhongshan District, Keelung, Taiwan. The power plant is the only fully oil-fired power plant in Taiwan.
Contents
Generation units
The power plant consists of four 500-MW generation units. The third 500-MW unit was finished on 19 December 1979 after a record-breaking construction period of 26 months. It went into operation in March 1980. The fourth 500-MW unit was completed in 1985 after 29 months construction period.
Components
The steam generator is rated at 1,701 tonne/hour, 176 kg/cm3 and 542 °C at superheater outlet and reheat to 542 °C.
The steam turbine is a tandem-compound with four flow exhaust, 3,600 rpm single reheat with throttle steam conditions of 166 kg/cm2, 538 °C with reheat to 538 °C.
The stacks are 200 meters high slip-form reinforced concrete stack.
Transportation
Hsieh-ho Power Plant is accessible North from TRA Keelung Station.