Country Taiwan Status Operational Primary fuel Oil Province Taiwan Province | Location Zhongshan, Keelung Operator(s) Taipower Phone +886 2 2424 8111 Owner Taiwan Power Company | |
Commission date January 1977 (Unit 1)
December 1977 (Unit 2)
March 1980 (Unit 3)
1985 (Unit 4) Address No. 80, Wenhua Rd, Zhongshan District, Keelung City, Taiwan 203 Hours Open today · Open 24 hoursThursdayOpen 24 hoursFridayOpen 24 hoursSaturdayOpen 24 hoursSundayOpen 24 hoursMondayOpen 24 hoursTuesdayOpen 24 hoursWednesdayOpen 24 hours Similar 大武崙漁港停車場, 外木山漁港, 仙洞巖最勝寺, 卞家牛肉麵, 基隆小羅牛肉麵 |
The Hsieh-ho Power Plant (Chinese: 協和發電廠; pinyin: Xiéhé Fādiànchǎng) is an oil-fired power plant in Zhongshan District, Keelung, Taiwan. The power plant is the only fully oil-fired power plant in Taiwan.
Contents
Generation units
The power plant consists of four 500-MW generation units. The third 500-MW unit was finished on 19 December 1979 after a record-breaking construction period of 26 months. It went into operation in March 1980. The fourth 500-MW unit was completed in 1985 after 29 months construction period.
Components
The steam generator is rated at 1,701 tonne/hour, 176 kg/cm3 and 542 °C at superheater outlet and reheat to 542 °C.
The steam turbine is a tandem-compound with four flow exhaust, 3,600 rpm single reheat with throttle steam conditions of 166 kg/cm2, 538 °C with reheat to 538 °C.
The stacks are 200 meters high slip-form reinforced concrete stack.
Transportation
Hsieh-ho Power Plant is accessible North from TRA Keelung Station.