High-speed rail in Indonesia

Plans and studies have been in the works for high-speed rail (HSR) in Indonesia since before 2010. A new plan to build a HSR was announced by Indonesian Government in July 2015. Indonesia's first — and possibly also Southeast Asia's first high-speed rail project — was expected to connect the national capital Jakarta with Bandung in neighboring West Java province, covering a distance of around 140 kilometres. Plans were also mentioned for a possible later extension of the HSR to Indonesia's second largest city, Surabaya in East Java.

Contents

Both Japan and China had expressed their interest in the project. Previously, both countries had carried out comprehensive studies for a project for the Jakarta-Bandung section (150 km). Only the Japanese agency, JICA, had issued a study for a project extending to Surabaya (730 km). The Indonesian HSR bid marked rivalry between Japan and China in their competition for Asian infrastructure projects.

On late September 2015, Indonesia awarded the rail project to China, much to Japan's disappointment. It was said that China’s offer to build the Jakarta-Bandung line without requiring an official loan guarantee nor funding from Indonesia was the tipping point of Jakarta's decision.

In January 2016, Transportation Minister released a route permit for a high speed railway between Jakarta-Bandung (142.3 kilometers) with stations located at Halim (Jakarta end), Karawang, Walini, and Tegalluar (Bandung end) and also Tegalluar depo. The better departure point at the Jakarta end would be the inner city railway station of Gambir but because construction of the Gambir-Halim leg was seen as adding complications, the link will only be from Halim (Jakarta) to Tegalluar (Bandung) with a cost of $5.135 million. Concession period is 50 years from May 31, 2019 and cannot be prolonged, except in force majeur situation. Groundbreaking has been done on January 21, 2016. The HSR is project of 60 percent of Indonesian consortium and 40 percent of China Railway International. The Jakarta-Bandung high-speed rail is planned to begin its operations to public in 2019. The Japanese proposal can start operation only by 2023. The section Bandung-Surabaya, though a priority section due to heavy congestion, has been officially shelved for budget reasons since early 2015.

In October 2016, Indonesian government has announced to build 600 km medium-high speed railway between Jakarta and Surabaya, and invited Japan to invest at this project.

JICA's proposal

Since 2008, Japan has been long-nurtured the plan to export their Shinkansen high-speed railway technology to Indonesia. During Indonesia-Japan Friendship Festival in November 2008, Japan has showcased their Shinkansen technology to impress Indonesian audiences. In 2009, a Japanese government-sponsored feasibility study was conducted for the planning of project — a high speed (300 km/hr) rail line extending 730 kilometers across the island of Java from Jakarta to Surabaya. The idea of high-speed rail backed by funding (soft loans) has been proposed by Japan International Cooperation Agency (JICA) for the Indonesian island of Java, linking up the densely populated corridor from the capital Jakarta to Surabaya (730 km). The island, similar in many respects to pre-HSR Honshu, suffers greatly from both freight and passenger congestion.

The idea has been around for some years, however, a new proposal to divide the project into stages has emerged, with the first stage from Jakarta to Bandung, 150 km to 35 minutes, from current conventional train time of 3 hours at a price of 50 trillion rupiah. The JICA detailed feasibility study was finished in 2014, following up on an initial study in 2012. By 2013 Indonesia has been undergoing a revival in railway expansion and upgrades in recent years. High-speed corridors have been proposed but not implemented.

Japan — with its reputation as a world-class train-maker — seemed destined to win the contract. However, in 2014 Indonesian government changes, as Joko Widodo swore as a new president in October 2014. In January 2015 the Joko administration essentially stopped preparations for the high-speed rail project, citing that the high-speed rail project is too costly and there are more pressing infrastructure needs in outlying underdeveloped islands outside of Java.

Japanese domination in high-speed rail project seemed to be unchallenged. However, that was until April 2015 when China had entered the race with a counter-offer.

In March, Joko Widodo traveled to Tokyo and Beijing. In Tokyo March 22–25 Joko Widodo met Japanese Prime Minister Shinzo Abe, Joko got a commitment for Japanese loan support for improving Jakarta's municipal rail network, but no progress was made on resolving issues with the Jakarta-Bandung high-speed rail project.

China's bid

In April 2015, China submitted a bid for the Indonesian high-speed rail project — much to Japan’s dismay.

On March 26, 2015, Joko Widodo visited Beijing and met Chinese president Xi Jinping. Xi publicly announced support for the Indonesian high-speed project and the two governments signed a memorandum specifying China's interest in the Jakarta-Bandung line.

In July 2015, Indonesian government exposed their plan to build the high-speed rail connecting Jakarta and Bandung, and arranged a contest between Japan and China train-makers as potential bidders. China responded by launching a Chinese High-speed Rail Technology exhibition in Senayan City shopping mall in Jakarta in August 2015.

Both China and Japan have engaged in a fierce competition through intense lobbying. It was said that the fundamental reason for the high level of assertiveness demonstrated by both Japan and China goes well beyond just economics — this contest is part of a much larger chess game the two Asian powerhouses are playing in pursuit of greater strategic influence within the Asia Pacific.

Short cancellation

President Joko Widodo was expected to announce the winning bid of Indonesia's first high-speed rail project in early September 2015. However, to everyone's surprise, on 3 September 2015 the Indonesian government announced that they had cancelled the high-speed rail project, citing that they are now looking to the slower and cheaper rail alternative. It was said that the government turns to semi-high-speed rail.

President Joko Widodo is wishing for a "business-to-business" approach, as opposed to "government-to-government" approach. Which signify government unwillingness to partially fund nor financially guarantee this costly project. After the cancellation, it seems that China secretly reapproaches Indonesia with a new offer, while Japan failed to do so.

Bid winner

In mid-September 2015, China said they would fully meet the Indonesian government's demands and offering new proposal that does not require Indonesia to assume any fiscal burden or debt guarantee in proceeding with the project. After months of bids, revisions and talks among presidents and prime ministers — even a short-lived cancellation of the project — in late September 2015 Indonesia picked China for the $5 billion project. It seems that Beijing has outmanoeuvred Tokyo on this bid as a result of a competitive financing package for Indonesia.

Japan's Chief Cabinet Secretary Yoshihide Suga termed the Indonesian move "difficult to understand" and "extremely regrettable". The situation "can only be described as extremely deplorable," Suga also said. According to Indonesia's State-Owned Enterprises Minister Rini Soemarno, Chinese bid was picked due to its financial structure — because the Chinese had not required any Indonesian government financing or a government guarantee, unlike the Japanese plan.

China's victory over Japan in this bid seems to owe mainly to Chinese willingness to accept the financial risk of the project. Which is to forego an Indonesian government guarantee and also, thereby, possibly to finesse international ODA norms, in contrast of Japan's inability or unwillingness to do so.

China has also sweetened its deal in other ways, including committing to establish a joint venture with Indonesian firms to produce rolling stock for high-speed rail, electric rail, light rail systems, not only for Indonesia, but also for export to other Asian countries — to transfer related technology — and to renovate and rebuild train stations. It seems that Indonesia has benefitted from Japan-China competition.

Progress in 2016

  • January. Indonesian president Joko Widodo attended a ground breaking ceremony near Jakarta and announced that the project had commenced.
  • May. Continual delays in acquiring land were being reported. The president of the Indonesian joint venture firm managing the project, PT KCIC (Kereta Cepat Indonesia China), Hanggoro Budi Wiryawan, expressed frustration at the Dept of Transport requirement that all of the land needed for the project (estimated to be 600 ha) be acquired before final construction permits could be issued. Hanggoro argued that it was more usual for construction permits to be issued when just 10% of the required land for a project had been acquired. He said that the delays in the Dept of Transport were unreasonable. Issues surrounding acquisition of land were complicated by the fact that the main station at the Jakarta end was planned to be on land occupied by the Indonesian Air Force at Halim Perdanakusuma. It was not clear whether the Air Force was prepared to release the land.
  • August. The Minister for State-Owned Enterprises, Rini Soemarno, said that the process of issuing permits for the project was running smoothly after earlier delays. She said that she believed that construction on the railway could start within a week.
  • November. 82 percent of land needed has been acquired, but bank funding will only be attainable after 100 percent land is acquired.
  • Jakarta-Bandung

    initial 4 stations due 2019:

  • Jakarta Halim Perdanakusuma Station incl. transfer to Airport Railway due 2019
  • Karawang
  • Tegalluar
  • Bandung Walini Station
  • Bandung Gedebage Station
  • Funding and joint venture

    The China Railway Construction Corporation Limited (CRCC) will form a joint venture with a consortium of Indonesia's state-owned enterprises (SOEs) led by PT Wijaya Karya Tbk (IDX: WIKA) in developing the first High Speed Train (HST) in the country.

    On Friday, 16 October 2015, Chinese and Indonesian state-owned companies officially signed the deal to build the first high-speed railway in Indonesia. The project cost was estimated to be US$5.5 billion (80 trillion rupiah). The deal was signed by China Railway International Co. Ltd. Chairman Yang Zhongmin and Dwi Windarto, the president director of a consortium of Indonesian state companies, PT Pilar Sinergi BUMN Indonesia. China Development Bank has given a commitment to fund 75 percent of the project costs with loan terms of 40 years for the loan—with an initial grace period of 10 years—with fixed loan rate. CRCC will hold majority shares in the planned JV company, while WIKA holds 30 percent and small portions for local toll operator PT Jasa Marga Tbk (IDX: JSMR), train operator PT Kereta Api Indonesia and plantation company PT Perkebunan Nusantara VIII.

    In late August 2016, it was reported that the China Development Bank had not yet disbursed funds for the loan and that PT Kereta Cepat Indonesia-China, the consortium executing the project, was not sure when funds would become available.

    References

    High-speed rail in Indonesia Wikipedia