Harman Patil (Editor)

HVDC BorWin2

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Country
  
Germany

Manufacturer of conductor/cable
  
Prysmian

Expected
  
2015

Number of poles
  
1

From
  
BorWin Beta platform

Manufacturer of substations
  
Siemens

Total length
  
200 km (120 mi)

Passes through
  
North Sea

HVDC BorWin2 httpsuploadwikimediaorgwikipediacommonsthu

Type of current
  
High-voltage direct current

Similar
  
North Sea, Mühlenheider Windkraftmuseum, Topography of Terror, Bochum Total, Tropical Islands Resort

HVDC BorWin2 is a high voltage direct current (HVDC) link built to transmit offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters are used and the total cable length is 200 km. The project was completed by the Siemens/ Prysmian consortium and handed over to its owner, TenneT, in January 2015, becoming the first such project to be completed (the earlier HVDC BorWin1 project, despite having completed construction in 2009, was still not fully in service by that date).

Contents

Context

BorWin2 is part of an ambitious programme of providing grid connections to offshore wind parks off the coast of Germany, in the German Bight, as part of the German Energiewende (Energy Transition) programme. BorWin2 forms part of the BorWin cluster, named after the German island of Borkum. BorWin2 has been built to transport power from the 400MW Veja Mate (using 6MW Siemens gearless turbines) and Global Tech 1 wind parks.

HVDC has been chosen for most of the grid connections because the relatively long distance involved – both from the wind park to shore and from the shore to the nearest suitable connection point to the onshore grid - makes conventional alternating current transmission uneconomic.

Technical aspects

BorWin2 uses Voltage Sourced Converters (VSC) to convert from AC to DC and back again, using 4.5kV IGBTs as the switching elements. One converter is provided at each end of the link with a DC voltage of ±300 kV and a transmission capacity of 800 MW. The converters, built by Siemens, use the Modular Multi-Level Converter technology, in the symmetrical monopole configuration. Each converter station is equipped with two, three-phase transformers, each rated at 590MVA (offshore) and 585MVA (onshore). Each converter valve is equipped with a dry-type valve reactor of 50mH.

The offshore converter is located on the BorWin Beta platform, which was built by Nordic Yards in Warnemünde. The topside of the platform is of the float-over type which is designed to be floated out to the installation site and then jacked up onto the submerged supporting structure using the support legs that are integral to the structure. The topside has a total weight of 12000 tonnes and measures 72.5 m x 51 m x 25 m high.

Each of the two 300 kV cables linking BorWin Beta to the onshore substation has a total length of 200 km, of which 125 km is sea cable and 75 km is underground land cable. The cables cross the small island of Norderney and, having reached the mainland, continue, as land cables, to the onshore converter station at Diele. The cables were supplied by Prysmian and use extruded Cross-linked polyethylene insulation.

Construction schedule

The BorWin2 project was ordered in 2010. The platform was installed in April 2014. Commissioning was completed in November 2014 and the project was handed over in January 2015.

References

HVDC BorWin2 Wikipedia