Country
  
Wales, United Kingdom

Commission date
  
18 June 2015

Site area
  
80 km²

Construction cost
  
2 billion EUR

Status
  
On-line

Type
  
Offshore

Construction began
  
January 2012

Gwynt y Môr Gwynt y Mr Offshore Wind Page 2

Location
  
off the coast of North Wales, UK

Operator(s)
  
Gwynt y Môr Offshore Wind Farm Limited

Owners
  
Npower, Stadtwerke München, UK Green Investment Bank, Siemens

Gwynt y Môr (English: Sea Wind) is a 576-megawatt (MW) offshore wind farm located off the coast of North Wales and is the second largest operating offshore windfarm in the world. The farm has 160 wind turbines of 150 metres (490 ft) tip height above mean sea level.

Contents

Gwynt y Môr Eye in the sky at Gwynt y Mor Offshore Wind reNEWS Renewable

Planning consent for the project was granted on 3 December 2008. The project has a value of 2 billion Euros, of which 1.2 billion Euros were spent on turbines and electrical connections. Construction began in 2012, power production started in September 2013, construction phase ended in November 2014, and final commissioning occurred in June 2015.

Gwynt y Môr innogy Wissenscloud

Design and planning

Gwynt y Môr Gwynt Y Mor HotelR

As with all offshore wind farms in the UK the Crown Estate owns the seabed at Gwynt y Môr. It has agreed to lease the land to npower renewables. The wind farm is located close to the existing North Hoyle and Rhyl Flats offshore wind farms. These projects are wholly or partly owned by RWE npower renewables, a subsidiary of German company RWE. In the case of Gwynt y Môr, RWE holds 50%, Stadtwerke München holds 30%, Siemens holds 10% and UK Green Investment Bank holds 10%.

Gwynt y Môr Gwynt y Mr Green Giraffe

With 160 turbines of 3.6MW Siemens SWT-3.6-107, Gwynt y Môr will be Wales' largest wind farm. The output of 1,950 GWh per year is capable of powering around 400,000 homes, or 30% of the homes in Wales. This prevents the release of about 1.7 million tonnes of carbon dioxide every year.

Gwynt y Môr Gwynt Y Mor HotelR

Planning consent for the project was granted on 3 December 2008. The project has a value of 2 billion Euros. 1.2 billion Euros will go to Siemens for turbines and electrical connections.

Two floating experimental LIDAR wind measurement stations have been tested at the site for two years.

Construction

Gwynt y Môr wwwoffshorewindbizwpcontentuploads201605Gw

Construction work began offshore in January 2011 when pieces of rock were laid on softer parts of the seabed to secure the foundations of the turbines. Work began on laying undersea cables from the windfarm to the shore in August 2012. In order to feed electricity into the national grid, a substation was built near St Asaph in Denbighshire.

Power production started in September 2013. Final commissioning was completed on 18 June 2015.