Trisha Shetty (Editor)

Guiyang–Guangzhou High Speed Railway

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Status
  
Operational

Opened
  
December 26th 2014

Locale
  
Guiyang, Guangzhou

Services
  
1

Line length
  
856 km (532 mi)

Guiyang–Guangzhou High-Speed Railway

Operator(s)
  
China Railway High-speed

Track gauge
  
1,435 mm (4 ft 8 ⁄2 in)

Terminis
  
Guangzhou South Railway Station, Guiyang East Railway Station

Guiyang-Guangzhou High Speed Railway, is a high-speed rail (HSR) line in southern China between Guiyang and Guangzhou, the provincial capitals, respectively of Guizhou and Guangdong Province. The line, also known as the Guiguang HSR, is dedicated to high speed passenger rail service. The line is 856 km (532 mi) in length and can carry trains at speeds of up to 250 km/h (155 mph). The line was built from 2008 to 2014 and opened on December 26, 2014.

Contents

The line traverses rugged karst terrain in Guizhou and Guangxi and relies on extensive bridges and tunnels, which comprise 83% of the line's total length. The travel time by train between the two terminal cities was reduced from 20 hours to 4 hours.

History

The Guiguang HSR was a major trunk route planned in the 11th Five Year Plan by the Chinese government. It is designed to serve as a rapid rail link between the southwest China and the Pearl River Delta. Construction began in 2008 and was completed in 2014. The line was built to accommodate train speeds of up to 250 km/h (155 mph), with the capacity to be remodelled to allow train speeds of up to 300 km/h (186 mph).

Route

The Guigang HSR takes a more direct route between its terminal cities, and crosses exceptionally difficult and mountainous terrain, which made construction very costly. The project cost an estimated 85.8 billion RMB (USD$12.5 billion), although this figure was later revised to 94.6 billion RMB (USD$13.8 billion).

The line runs from Guangzhou through Foshan, Sanshui and Zhaoqing in the densely populated Pearl River Delta and then crosses the Lingnan mountain range via Huaiji into Guangxi. It continues in a northwesterly direction through Hezhou and Zhongxiang to the famed scenic cities of Yangshuo and Guilin and then on to Sanjiang. The line enters Guizhou at Congjiang near the southeast tip of the province and passes Rongjiang, Sandu, Duyun, and Longli on to Guiyang in the center of the province.

This line traverses 270 tunnels and 510 valleys across the karst landscape. Bridges and tunnels account for 83% of the line's total length, including 92% in Guizhou Province. A total of 238 tunnels, totaling 464 km, were built along route including nine tunnels over 10 km in length. The longest tunnel, through the Yan Mountain in Rongjiang, is 14.693 km.

References