Puneet Varma (Editor)

Braemar Power Station

Updated on
Edit
Like
Comment
Share on FacebookTweet on TwitterShare on LinkedInShare on Reddit
Country
  
Australia

Primary fuel
  
Coal seam gas

Owner
  
Status
  
Operational

Combined cycle?
  
No

Braemar Power Station

Location
  
Commission date
  
2006 (Braemar-1)2009 (Braemar-2)

Address
  
363 Graham's Road, Kogan QLD 4406, Australia

Similar
  
Darling Downs Power St, Kogan Creek Power St, Origin Chinchilla, Lake Broadwater Conserva, QGC

Braemar Power Station is a complex of natural gas and coal seam gas fired combined-cycle power stations near Dalby in the Darling Downs region of Queensland, Australia.

Contents

Braemar-1

Braemar-1 is a 502 MW open-cycle natural gas turbine plant located 35 kilometres (22 mi) south west of Dalby, adjacent to the Kogan Creek Power Station, Queensland – New South Wales high voltage transmission interconnector and Power Link 320/274 kV substation. It is supplied from the Tipton West coal seam gas fields, with the 150-kilometre (93 mi) pipeline between Condamine and Braemar, which is used exclusively to supply the Braemar Power Station.

The power station was developed by ERM Power and was built by Alstom. It is equipped by three Alstom's 150 MW GT13E2 gas turbines. The power station cost A$545 million. It was completed in 2006 and is anticipated to operate until 2036. ERM Power sold the plant to Alinta Energy in 2008.

Braemar-2

Braemar-2 is a 450 MW open-cycle natural gas turbine plant adjacent to the Braemar-1 power station. The power station was developed by ERM Power and was built by Bilfinger. It supplies peak demand power and it is equipped by three Siemens's 150 MW SGT5-2000E gas turbines. The power station cost A$546 million. Gas for this power station is sourced from the Stratheden field at Daandine.

Braemar-2 began operating on 12 June 2009 and was officially opened on 25 August 2009. It is Queensland's second-largest gas-fired power station. Arrow Energy acquired 50% of the station in 2008 and on 4 July 2011, it took full control of Braemar-2.

Braemar-3

Braemer 3 is a planned 550 MW power station adjacent to the existing stations. It is expected to by operational be 2015 and cost $530 million to build. The final investment decision will be made in 2013.

Braemar-4

ERM Power is considering the development of Braemer 4, indicating it will proceed with its development when market conditions improve.

References

Braemar Power Station Wikipedia


Similar Topics