Country United States | Owner(s) Kentucky Power Company Cooling source Big Sandy River | |
![]() | ||
Commission date 281 MW (1963)816 MW (1969) Similar Muskingum River Power Pl, Tanner's Creek Generatin, J Robert Welsh Power Pl, E W Brown Generatin, Ghent Generating Station |
Implosion of unit 2 at big sandy power plant in louisa
The Big Sandy Power Plant is a Natural gas fired Power station owned and operated by American Electric Power near Louisa, Kentucky. It was established in 1963. It was formerly a coal fired plant, but was converted to natural gas in 2016.
Contents
- Implosion of unit 2 at big sandy power plant in louisa
- Blast sends cooling tower crumbling down at big sandy power plant
- Plant DataEdit
- Emissions DataEdit
- Conversion to natural gasEdit
- References

Blast sends cooling tower crumbling down at big sandy power plant
Plant DataEdit

Emissions DataEdit


In January 2009, Sue Sturgis of the Institute of Southern Studies compiled a list of the 100 most polluting coal plants in the United States in terms of coal combustion waste (CCW) stored in surface impoundments like the one involved in the TVA Kingston Fossil Plant coal ash spill. The data came from the EPA's Toxics Release Inventory (TRI) for 2006, the most recent year available.

Big Sandy Plant ranked number 40 on the list, with 915,079 pounds of coal combustion waste released to surface impoundments in 2006.
Big Sandy Plant's Fly Ash surface impoundment is on the EPA's official June 2009 list of Coal Combustion Residue (CCR) Surface Impoundments with High Hazard Potential Ratings. The rating applies to sites at which a dam failure would most likely cause loss of human life, but does not assess of the likelihood of such an event.
The data came from the EPA's Toxics Release Inventory (TRI) for 2006, the most recent year available.
Conversion to natural gasEdit
There is a discussion regarding a proposal to convert coal fired plants such as Big Sandy to natural gas to reduce fuel costs, greenhouse gas emissions, and airborne toxins. Initially Big Sandy's owner AEP proposed a billion dollar upgrade to allow it to continue to burn coal, however this upgrade was opposed by environmentalists, and also opposed by electricity consumers who oppose higher rates to pay for the upgrade.
Later AEP agreed to convert to natural gas. Gas is supplied by Columbia Natural Gas and the contractor building the pipeline and valve stations is Eagle Pipeline (contracted by Columbia). Big Sandy's conversion to natural gas was supported by New York City Mayor Michael Bloomberg, as New York is a consumer of Big Sandy's electricity.
Conversion to natural gas was completed on May 30, 2016.