Country Belgium | Owner(s) Belwind NV | |
![]() | ||
Location Ostend, Zeebrugge region, North Sea Status Operational (phase 1)
Planned (phase2) Commission date 9 December 2010 (2010-12-09) Site area 13 km (5 sq mi) (phase 1)
22 km (8 sq mi) (phase 2) |
Belwind alstom haliade demonstrator
The Belwind Wind Farm is located on Bligh Bank, 46 kilometres (29 mi) from the Belgian port of Zeebrugge, and will be built in two phases. When completed, it is expected to have a 330 MW production capacity and an estimated annual output of 1.1 TWh. Phase 1 has a 165 MW production capacity.
Contents
- Belwind alstom haliade demonstrator
- Geosurveyor 10 belwind
- Financing
- Status First Phase
- Status Second Phase
- Revenue
- References

Geosurveyor 10 belwind
Financing

Bligh Bank is the first stage of what is planned to be a 330 MW project. It was financed under a Project Finance structure by Project Company ‘Belwind’, after a number of delays that included bankruptcy of developer Econcern. Financial close was eventually reached on July 27, 2009. Bligh Bank is only the third offshore wind farm to be Project Financed, following Q7 and Thornton Bank. The €614 million deal sees Colruyt Group, the Colruyt family, SHV, ParticipatieMaatschappij Vlaanderen (PMV), Meewind and Rabo Project Equity, come together to invest in the construction of the 165 MW first stage of the Project. For the first time the European Investment Bank will assume project finance risk for an offshore wind farm, by granting €300 million towards financing the Project.

In January 2011 SHV sold its 20,7 % equity-share to the other Belgian shareholders Colruyt Group, the Colruyt family and ParticipatieMaatschappij Vlaanderen (PMV).
Status First Phase

Construction of the first phase commenced in August 2009 and was completed on 9 December 2010. The wind farm includes an Offshore High Voltage Station (OHVS ) which converts the infield 33kV to the export cable (150kV). This export cable is connected to the second high-voltage station, (the Booster Transformer Station) in Zeebrugge. In 2012 Alstom planned to install a wind turbine of 6 MW Haliade as a test, which happened in November 2013.
Status Second Phase
The financial close of the Second Phase of the project is expected in 2015, constructing is planned in 2015-2017.
It is unclear if the electricity network in Belgium is ready for the connection of more windfarms at this moment. According to Elia the Stevin project needs to be finished to have a reliant enough electricity grid in place to connect any new wind farms in the future. The Stevin project concerns a new 380kV network to the Belgian coast.
Revenue
The Belwind Wind Farm has a green certificate, meaning it will receive a set minimum price through Elia, €107 per MWh for the first 216 MW, the remaining 114 MW will receive €90 per MWh. In 2011 it received €49,51 per MWh through the sale of the generated electricity to Electrabel.