Park section
  
Gloomy Wood

Opening date
  
2018

Designer
  
Merlin Magic Making

Cost
  
15 million GBP

Status
  
Under construction

Type
  
Wood

Opened
  
2018

Replaced
  
The Flume

SW8 (roller coaster)

Lift/launch system
  
Silent magnetic lift system

Address
  
Haunted Hollow, Stoke-on-Trent ST10 4DB, UK

Similar
  
Galactica, Thirteen, Nemesis, The Smiler, Oblivion

SW8 (Secret Weapon 8) is the code name for a wooden roller coaster currently under construction at Alton Towers in Staffordshire, United Kingdom. The ride will replace The Flume which closed towards the end of the 2015 season. The attraction is set to be the park's first roller coaster constructed from wood and is confirmed to be manufactured by Great Coasters International. The ride is expected to open in late March or early April 2018.

Contents

Development

Originally, the park had planned to install a roller coaster in Forbidden Valley nearby Nemesis for the 2017 season, however due to many factors including budget, these plans were later dropped.

The Flume closed in early October 2015, 1 month before the end of the season and for the start on the 2016 season, it had been fenced off and surrounded by signs advertising the development of SW8. The site remained unchanged throughout the 2016 season.

The first planning documents were submitted to Staffordshire County Council on 23 April 2016. They documented the basic layout of SW8 and the surrounding area. They also suggested that the old station used for The Flume would be turned into a 'Smokehouse' restaurant however this indication was removed on later revisions, and The Flume station was fully removed. The full plans were submitted on 31 May 2016 and were approved on the 24 August 2016.

It was rumoured online that SW8 was to take the theme of 'The Wicker Man', however this has not been confirmed.

It was revealed in the 2017 Alton Towers map that SW8 will be a part of Gloomy Wood

Construction

Construction of SW8 commenced on 28 November 2016 with the demolition of The Flume. The construction site covers the site of the old The Flume ride, employee entrance gates in Mutiny Bay, the path connecting Mutiny Bay and Katanga Canyon and Magic HQ car park.

The project went vertical with station construction in early March 2017.