Commission date 29 October 2011 Nameplate capacity 200 MWp Construction began 20 August 2009 | Status Operational Site area 5.64 km² Construction cost 3.26 billion CNY | |
Owner State Power Investment Corporation |
Huanghe Hydropower's Golmud Solar park is a 200 megawatt (MW) photovoltaic power station located in Golmud, Qinghai Province, China. Construction began in August 2009, and it was commissioned on October 29, 2011. 80 MW was provided by Yingli. The project won the 2012 China Quality Power Project Award. Output is expected to be 317 GWh per year.
Also in Golmud is the 20 MW Qinghai Golmud Solar Park completed in 2011 by Longyuan Power, as well as others. There are a total of 570 MW of solar parks in Golmud, many of which are located in the Golmud Desert Cluster, with 500 MW more expected in 2012.[update needed]
References
Huanghe Hydropower Golmud Solar Park Wikipedia(Text) CC BY-SA