Country United States Commission date 1998 | ||
![]() | ||
Status Shutdown in 2000, sale to GVEA pending Owner(s) Alaska Industrial Development and Export Authority (AIDEA) Primary fuel Usibelli Sub-bituminous coal |
Healy Clean Coal Project is a clean coal technology demonstration program consisting of a coal fired electrical power station located in Healy, Alaska in Denali Borough. The project was a demonstration of the TRW Clean Coal Combustion System and the Babcock & Wilcox/Joy Spray Dryer Absorber (SDA) System designed to reduce oxides of nitrogen (NOX) and sulfur dioxide (SO2) emissions while burning a variety of coal types, including waste coal.
The project constructed a plant adjacent to Golden Valley Electric Association (GVEA) 25 MW coal plant Healy Unit 1. Construction occurred from 1995-1997 at a cost of around $300 million. The facility operated briefly following its construction as part of the demonstration program, but has been shut down since 2000. The research project is considered "complete" by the Department of Energy. The plant is being sold to the GVEA to resume power production in 2012.
Costs
According to Golden Valley Electric Association (GVEA) the facility cost around $300 million, with the United States Department of Energy contributing $120 million, the Alaska Legislature contributing $25 million, the Alaska Industrial Development and Export Authority (AIDEA) contributing $150 million and both GVEA & Usibelli Coal Mine contributing $10 million in addition to in-kind contributions.